Why do many people think PDA only works on driven piles?

Because of the instrument's name and site convenience, not because of any limitation in the principle. PDA stands for Pile Driving Analyzer, which was developed specifically to monitor pile driving, so the name has been tied to the word "driving" from the start. The other reason is that driven-pile jobs already have a piling rig and hammer on site, so testing can start right away with almost no extra preparation.

Installing strain gauges and accelerometers on the side of a bored pile for High Strain PDA testing
Installing gauges on the side of a bored pile before PDA testing (Photo: SPN Soil Engineering)

The test principle does not depend on how the pile was installed. Dynamic Load Test (PDA) applies an impact to the pile head and measures the stress wave travelling down and reflecting back, in order to calculate the mobilized load capacity. Whether the pile was driven or cast in a bored hole, the wave travels through the concrete in the same way.

Both ASTM D4945 (Standard Test Method for High-Strain Dynamic Testing of Deep Foundations) and DPT 1252-51 are written to cover deep foundations in general; neither states that it applies only to driven piles.

How does testing a bored pile differ from a driven pile?

The measurement and analysis principles are exactly the same. The differences lie in four aspects of site preparation: the impact source, hammer weight, pile head preparation, and impact cushioning.

Crane lifting a drop weight above a bored pile head, ready to strike for High Strain testing
Bored pile sites have no piling rig, so a test hammer must be brought in and set up above the pile head (Photo: SPN Soil Engineering)

1. The hammer must be brought in and set up — Driven-pile jobs use the hammer of the piling rig already on site, but bored pile sites have no driving equipment. The test team must therefore bring a test hammer with a guide frame and a crane and set them up above the pile head. This takes up space and requires crane access.

2. The hammer must be heavy enough to mobilize capacity — Bored piles usually have larger cross-sections and carry higher loads than driven piles on the same project, so the hammer must be heavy enough to move the pile down slightly with every blow. If the pile does not move at all, the capacity has not been fully mobilized and the result is only a proven minimum, not the true ultimate capacity.

3. The pile head needs more preparation — The top of a bored pile carries a layer of laitance and sediment from the concreting process. It must be trimmed back to sound concrete and the surface made flat and perpendicular. Full details are in the article Pile head preparation before testing

4. Impact cushioning is required — A pile head plate and a cushion such as plywood are placed between the hammer and the pile head to spread the force and lengthen the impact duration so the pile head does not crack. Cushion thickness directly affects the recorded waveform.

For an overview of which test method suits each pile type, read Bored pile vs driven pile: how testing differs

The figure below brings all four aspects together in one picture. Reading from top to bottom: the test hammer in its guide frame, the cushion on the pile head trimmed to sound concrete, and the opposing gauge pairs in the pit excavated around the pile head. The box on the right summarizes how each point differs from driven-pile work.

Conceptual side view of a bored pile prepared for a High Strain Dynamic Load Test (PDA), with the specific points that differ from driven piles A two-panel diagram with a bottom strip. The left panel is a conceptual side view of a large bored pile in a pit excavated around the pile head. The pile head has been trimmed back to sound concrete and made flat and perpendicular to the axis. Plywood cushioning and a pile head plate sit on the pile head. Above them, a guide frame keeps the test hammer aligned with the pile axis; the hammer hangs from a crane sling. A dashed arrow shows the drop height, which starts low and is increased step by step. On the side of the pile in the pit, below the pile head, orange strain gauges and blue accelerometers are attached in opposing pairs on two sides, with signal cables running up to the PDA unit on the ground. Inside the pile, stress-wave arrows travel down and reflect back, and green arrows represent soil resistance mobilized when the pile moves down slightly. The right panel summarizes four points specific to bored piles: A, the pile head has laitance and sediment that must be trimmed back to sound concrete and made flat and perpendicular; B, the impact may be eccentric, so gauges are attached in opposing pairs to average the result, shown by a horizontal section with an off-center impact point; C, bored piles have large cross-sections, so the hammer must be heavy enough to move the pile down slightly every time, and if it does not move the result is a proven minimum capacity; D, the concrete must have sufficient age and strength, and the stress in the pile must be monitored at every blow. The bottom strip states that the same standards as for driven piles apply, namely ASTM D4945 and DPT 1252-51; that analysis is in two stages, with the Case Method on site and CAPWAP in the office; and that the hammer weight, drop height and pile head cushion are set by the testing engineer for the actual job. This is a conceptual figure, not a construction drawing. Bored pile ready for High Strain testing: preparation and differences from driven piles Not to scale Side view: bored pile head in the test pit Conceptual · not to scale PDA unit C Test hammer Set up on site, no rig Drop height Low → step up Plywood + pile head plate Spreads load · longer blow Pit around head For gauge access D Pile concrete Age + strength OK Crane sling Guide frame Keeps hammer on axis A Sound pile head Flat · perpendicular B Gauge pairs Strain Gauge + Accelerometer Below pile head Stress wave Down and reflected back Soil resistance Bored-pile specifics How it differs from driven piles A Laitance + sediment on head Trim back to sound concrete Make flat, perpendicular to axis Tilted face = unusable signal B Impact may be eccentric Gauges in opposing pairs To average off-center force Gauges firmly fixed to pile C Large section, high load Hammer must move pile down slightly with every blow No movement = proven minimum D Concrete strong enough Check age + strength first Monitor pile stress at every hammer drop 1 Same standards as driven ASTM D4945 · DPT 1252-51 2 2-stage analysis Case Method on site → CAPWAP 3 Hammer · drop · cushion Set by the testing engineer
Conceptual side view of a bored pile ready for High Strain testing: pile head trimmed to sound concrete, plywood and pile head plate placed, hammer set in a guide frame, and strain gauges and accelerometers attached in opposing pairs below the pile head — a conceptual figure, not a construction drawing. Hammer weight, drop height and cushion are set by the testing engineer for the actual job.

What are the steps of High Strain testing on a bored pile?

The test has 7 main steps, starting with checking concrete strength and preparing the pile head, followed by attaching gauges and setting up the hammer, and ending with dropping the hammer and analyzing the results with CAPWAP.

  1. Check concrete age and strength — The pile must be strong enough to take the impact without damage. See the criteria in How many days after casting can a pile be tested?
  2. Trim and prepare the pile head — Trim back to sound concrete and make the surface flat and perpendicular to the pile axis.
  3. Expose the pile side — Excavate the soil around the pile head to expose enough pile shaft to fix the gauges below the pile head.
  4. Install the gauges — Fix strain transducers and accelerometers in opposing pairs around the pile to average out the effect of an eccentric impact.
  5. Set up the hammer and guide frame — Align the hammer with the pile axis and place the pile head cushion.
  6. Drop the hammer and record signals — Start from a low drop height and increase it step by step, while monitoring the stress in the pile so it does not exceed a safe level.
  7. Analyze the results — Make a preliminary assessment on site with the Case Method, then a detailed analysis with CAPWAP in the office.
Engineering team recording PDA signals from the Pile Driving Analyzer during on-site testing
Force and velocity signals are recorded at every hammer blow and then analyzed further with CAPWAP (Photo: SPN Soil Engineering)
SPN staff holding a Dynamic Load Test record board showing the pile number, pile type, design load and test date, next to the test hammer on site
Every test must record the pile number, pile type and design load together with the site photos (Photo: SPN Soil Engineering)

For how to read the values in the report, see How to read PDA test results

The model below places all 7 steps on a single site. The numbered tags in the figure match the work sequence in the box on the right. Note that the crane needs a place to stand on ground that can carry it, and the signal cables must run from the test pit to the PDA unit — which is where the limitations in the next section come from.

Conceptual 3D model of a High Strain (PDA) test site on a bored pile, from the pit excavated around the pile head and the test hammer in a guide frame hanging from a crane to the PDA unit, with the work sequence on test day Conceptual 3D view of a soft-ground site with ponded water on the surface. The front corner of the soil block is cut away to show the pit excavated around the head of a large bored pile; the pit bottom is muddy with standing water. The pile head has been trimmed back to sound concrete, with a cushion and pile head plate on top. Above it is a four-post guide frame with the test hammer hanging inside, and orange dashed arrows show the hammer being dropped. The guide frame hangs from the sling of a crawler crane standing on the ground at the back right. On the side of the pile in the pit, orange strain gauges and blue accelerometers are attached in opposing pairs, with signal cables running up the pit wall to the PDA unit on the ground at the left, where two test team members stand. Numbered tags in the figure link to the box on the right, which lists the seven test-day steps from the article: one, check concrete age and strength; two, trim and prepare the pile head flat and perpendicular; three, expose the pile side around the head; four, attach opposing gauge pairs; five, set up the hammer and guide frame and place the cushion; six, drop the hammer starting from a low height and increasing step by step while monitoring stress; seven, assess preliminarily with the Case Method on site, then analyze in detail with CAPWAP. The bottom of the box states that PDA results on bored piles are used together with or compared against a Static Load Test when the project specification requires it, or when the pile is too large for the hammer to fully mobilize its capacity. This is a conceptual figure, not an actual site layout. 3D model: PDA site on a bored pile + test-day sequence Not to scale 5 Hammer + frame Set up on site, on axis 6 Drop hammer + record Low drop → step up Lifting crane Needs space + access Soft ground is a risk 7 PDA unit + test team Case Method: instant results Soft ground Waterlogged: harder setup + access 2 Sound head + cushion Trim, flat, perpendicular 4 Gauge pairs Strain Gauge + Accelerometer 3 Pit around head Front wall cut away Test day: sequence 1 Check concrete age + strength Pile must take the impact 2 Trim + prepare pile head Sound, flat, perpendicular 3 Expose pile side Enough shaft to fix gauges 4 Attach opposing gauges Average eccentric impact 5 Set hammer + guide frame Align on axis · place cushion 6 Drop hammer + record Low → high drop · watch stress 7 Case Method on site then detailed CAPWAP analysis PDA results on bored piles → use with/vs Static Load Test when the spec requires it, or when the pile is too large for the hammer to fully mobilize capacity Conceptual · not an actual site layout
Conceptual 3D model of a PDA test site on a bored pile: pit excavated around the pile head, hammer in a guide frame hanging from a crane, opposing gauge pairs and the PDA unit, with the 7-step work sequence on test day — a conceptual figure, not an actual site layout

What are the limitations of PDA on bored piles?

There are three main limitations: very large piles may not be fully mobilized, the site needs room for a crane, and the result depends on signal quality.

⚠️ 3 limitations to know before choosing this method
  • Very large piles may not be fully mobilized — The larger the pile and the higher its capacity, the heavier the required hammer, to the point where it may not be cost-effective or the site cannot accommodate it. In that case the result is only a proven minimum capacity.
  • Requires space and a crane — Unlike driven piles, which use the existing piling rig, a crane may not be able to set up on a cramped site or soft ground.
  • Results depend on signal quality — A poorly prepared pile head, a tilted face or loosely fixed gauges make the signal unusable and require a retest.
Dynamic Load Test on a soft, waterlogged site, with the drop weight hanging above the pile head in the test pit
A soft, waterlogged site makes it harder to set up the hammer and access the pile head (Photo: SPN Soil Engineering)

If the pile is too large for the hammer to fully mobilize its capacity, the alternative is a Static Load Test, which applies real load to the pile head. It gives the most direct result but takes more time and budget. For details on setting up the reaction system, read Kentledge vs reaction pile: what's the difference?

Many projects therefore combine the two methods: a Static Load Test on a sample pile, with PDA covering the other piles as required by the specification. The pros and cons of each method are compared in Dynamic vs Static Load Test: which to choose?

Can PDA tell you the integrity of a bored pile?

Not directly. Testing capacity and testing integrity are two separate things.

PDA answers the question how much load can the pile carry, but it does not directly answer whether the pile is sound along its full length. For bored piles, which are cast in a hole and cannot be seen during concreting, integrity is just as important as capacity.

Bored pile projects therefore usually run two tests side by side: PDA for capacity, and Seismic Integrity Test or Cross Hole Sonic Logging (CSL) for integrity. CSL gives more detailed results but requires access tubes cast into the pile, so it must be planned in advance.

Comparison table: PDA on bored piles vs driven piles

The standards and analysis principles are the same. What differs is the impact source, pile head preparation, retesting and the main limitations.

← Scroll to see the full table →

TopicDriven pileBored pile (cast-in-place)
Reference standardsASTM D4945 / DPT 1252-51ASTM D4945 / DPT 1252-51 (same)
Impact sourceHammer of the piling rig already on siteTest hammer must be brought in with a guide frame
Pile head preparationTrim concrete cracked by drivingTrim laitance and sediment, re-square the face
Retest (Restrike)Possible; used to check soil set-upNot normal practice
Main limitationEOD results may underestimate true capacityVery large piles may not be fully mobilized
Companion integrity testSeismic Integrity TestSeismic Integrity Test or CSL
Test drop weight hanging in a guide frame above an exposed pile head, ready to strike for a Dynamic Load Test
Test hammer with guide frame set up above the pile head — bored pile sites have no piling rig, so the hammer must always be brought in (Photo: SPN Soil Engineering)

For more on Restrike and soil set-up in driven piles, read What is a Restrike Test?

How much does PDA testing of a bored pile cost?

SPN's PDA service starts at approximately THB 5,500 per pile. A Static Load Test is approximately THB 50,000-150,000 per pile and up, depending on the test load and reaction system, and a Seismic Integrity Test is approximately THB 100-150 per pile.

This price excludes travel and equipment mobilization costs, which are charged extra depending on the distance to site.

For bored piles, the actual cost also depends on the hammer size required and site access. Send the pile size, length and design load to SPN's engineering team for assessment and receive a free quotation within 24 hours. See the full range of services on the pile testing services page.

⚠️ This article provides general information

This content explains the principles and practice of High Strain testing on bored piles for general understanding. The appropriate hammer weight, the number of piles to test and the acceptance criteria for each project must be set by the responsible engineer and stated directly in that project's specification.