Frequently asked questions about geotechnical design
What soil data is needed for foundation design?
Foundation design needs a boring log with SPT N-values for every soil layer, laboratory results (Atterberg limits, consolidation test, triaxial or direct shear) and the groundwater level. If you do not have soil data yet, SPN plans the number and depth of boreholes for the design and carries out the soil investigation in the same project.
What is slope stability analysis and when is it needed?
Slope stability analysis calculates the factor of safety (FS) of a soil slope or embankment, using Slope/W or PLAXIS. It should be done before building embankments, roads on soft clay, cut slopes and any deep excavation.
What factor of safety is required for slope stability?
A common reference is FS ≥ 1.5 for permanent slopes in the long-term (drained) condition, and about 1.2 to 1.3 for temporary slopes or during construction (short-term, undrained). Rapid drawdown and earthquake cases use specific criteria from the referenced standard. The value used depends on structure importance and project risk.
What is PVD with preloading and how does it help on soft clay?
PVD (prefabricated vertical drain) is a vertical drainage strip installed into soft clay with a steel mandrel, combined with a temporary surcharge fill to accelerate consolidation. It can reduce the waiting time from several years to 3 to 12 months. It suits roads and airports on the soft clay of central Thailand.
What is the difference between a sheet pile wall and a diaphragm wall?
A steel sheet pile wall is quick to install and lower in cost, but water can leak through the interlocks. A diaphragm wall is a reinforced concrete wall cast in a slurry trench: it is stiffer, more watertight and deforms less. It suits very deep excavation in urban areas.
What must be designed for a deep excavation next to existing buildings?
You need an earth retaining system (for example sheet piles, a contiguous pile wall or a diaphragm wall), a bracing system and a dewatering system. The design must check basal heave and estimate settlement of neighbouring buildings. Inclinometers and settlement points monitor the work.
What loads must be checked in solar farm pile design?
Besides compression, solar farm piles must be checked for uplift from wind, and for lateral load and moment at the pile head, using the Broms or p-y curve method with actual soil data. Tension reinforcement must also be checked. The design should be confirmed with field uplift and lateral load tests.
Can SPN's design be used for a building permit?
Yes. Design reports and construction drawings are signed by a licensed civil engineer (Council of Engineers Thailand licence) and can be submitted to the SAO, municipality, Bangkok Metropolitan Administration and other relevant authorities.
How long does a foundation design take?
A typical house takes 3 to 7 working days after complete soil data is received. Commercial buildings take 1 to 2 weeks and industrial plants 2 to 4 weeks. SPN can run the soil investigation and design in parallel to shorten the overall schedule.