What Is a Static Pile Load Test?
A Static Pile Load Test (testing pile load capacity by the static method) applies real static load to the pile head in increments and measures the resulting settlement to build a load–settlement relationship (Load-Settlement Curve) and assess the pile's load capacity per ASTM D1143 and DPT standard 1251 (for axial compression).
In the construction industry it is often simply called a Static Test or Pile Load Test, where Pile Load Test is the umbrella term for all types of pile load capacity testing. The static method is the original and most straightforward form because it directly measures the actual load-bearing behavior. The Static Load Test is therefore regarded as the most accurate and reliable method and serves as the "reference standard" for calibrating results from dynamic methods such as PDA.
What Reaction Systems Are Used in a Static Load Test?
There are 2 main reaction systems: kentledge and anchor piles. Both provide the reaction against which the jack pushes down on the pile head:
- Kentledge (dead weight) — a weight platform, such as concrete or steel blocks, is placed above the pile, and the jack pushes up against it. Suitable for moderate test loads where there is room to place the weight.
- Reaction / Anchor Pile — anchor piles are installed around the test pile and tied to a reaction beam, and the jack pushes against the beam. Suitable for high test loads.
The choice of system depends on the test load, site space and transport of the kentledge. See a comparison and installation steps for each at Kentledge vs Reaction Piles — Which Static Load Test Setup Is Better?
Kentledge System on Real Sites
Reaction / Anchor Pile System on Real Sites
How Is Load Applied in a Static Load Test?
The most common method is Maintained Load: load is added in increments, e.g. 25% of the design load per increment, with each increment held until settlement stabilizes before the next is added. There are 3 main loading procedures:
- Maintained Load (ML / Slow ML) — load is added in increments, each held until settlement stabilizes. This is the standard and most widely used method.
- Quick Maintained Load (QML) — each increment is held for a short, fixed time, so testing is faster.
- Constant Rate of Penetration (CRP) — the settlement rate is controlled to remain constant; suitable for determining ultimate capacity.
A proof test usually loads to 2–3 times the design load (depending on each project's specification), while a test to determine ultimate capacity loads the pile until it fails or settles to the criterion. The load is then released in increments to measure rebound and residual settlement.
Which Formulas Are Used to Interpret a Static Load Test?
There are 3 key formulas: elastic shortening of the pile, the Davisson criterion and the allowable working load. All are used to separate the elastic shortening of the pile itself from settlement caused by the soil:
How Do You Read the Load-Settlement Curve?
The load–settlement curve is the main result of the test. It shows the ultimate capacity, the settlement at the test load and the residual settlement after unloading. Common methods to determine ultimate capacity include:
- Davisson Offset Limit — the most widely used criterion: a line is drawn parallel to the elastic shortening line and shifted by an offset.
- Settlement Criteria — e.g. limiting total settlement or residual settlement to a specified value.
- Other methods — e.g. Chin-Kondner and Brinch Hansen 80% for mathematical estimation.
For an in-depth look at reading the curve and step-by-step interpretation examples, continue to How to Read Static Load Test Results — Load-Settlement Curves and Davisson. If the results fail the criteria, see the check sequence and remedial options at Failed Static Load Test? What to Do
The diagram below links the loading method to reading the results. The left side shows load added in increments and settlement over time, which must stabilize at every increment. The right side plots the end value of each increment as a Load-Settlement curve and finds its intersection with the Davisson line, offset from the PL/AE line by (4 + D/120) mm. (The 4 mm is rounded from 0.15 in ≈ 3.8 mm in Davisson's original.)
What Are the Steps of a Static Load Test?
Testing one pile involves 6 main steps, from installing the reaction system to preparing the report:
- Install the reaction system (kentledge or reaction piles + reaction beam)
- Place the hydraulic jack with a load cell on the test pile head
- Install settlement gauges (dial gauges/LVDTs) at 2–4 points on independent reference beams
- Apply load in increments, hold each until settlement stabilizes, and record readings
- Increase to the test load (2–3 times per the project specification, or to failure), then unload in increments
- Plot the Load-Settlement curve, analyze with Davisson and prepare the report
The 3D view below shows the full equipment set on test day. The front corner of the weight blocks is cut away to reveal the jack and load cell beneath the main beams. Note that the reference beams and settlement gauges are set up independently of the weight platform and cribbing, while the hydraulic pump and datalogger are placed away from the platform.
What Are the Advantages and Limitations of a Static Load Test?
The main advantage is accuracy from measuring actual behavior; the main limitations are time and cost:
The most accurate and reliable method, because it directly measures actual load-bearing behavior. It is the reference standard used to calibrate other methods and provides a complete Load-Settlement curve.
Time-consuming (possibly several days per pile), costly, and requires a large reaction system, so usually only selected sample piles are tested, and sufficient site space must be prepared. See the timeline for each step at How Many Days Does a Static Load Test Take?
Static Load Test fees are generally about THB 50,000–150,000+ per pile, depending on the test load, reaction system and site conditions. This price excludes travel and equipment mobilization, which are charged extra based on the distance to the site. See prices for each pile test method at Pile Testing Prices 2026
Which Standards Apply to a Static Load Test?
Axial compression Static Load Tests in Thailand refer to 2 main standards: ASTM D1143 and DPT standard 1251:
- ASTM D1143/D1143M-20e1 (Standard Test Methods for Deep Foundation Elements Under Static Axial Compressive Load) — specifies the loading system, incremental loading procedure, settlement measurement and reporting.
- DPT standard 1251 (Standard for Static Load Testing of Pile Bearing Capacity) of the Department of Public Works and Town & Country Planning — widely referenced on construction projects in Thailand.
The test report must state the standard used, the test load and the Load-Settlement curve. SPN reports are certified by a civil engineer holding a professional engineering license (COE) from the Council of Engineers Thailand and can be submitted for building permits to the relevant authorities. See further legal requirements at The Foundation Ministerial Regulation B.E. 2566 (2023) and Pile Testing
How Does a Static Load Test Differ from Other Pile Test Methods?
A Static Load Test measures load capacity with real load and is the reference standard, while other methods focus on speed and the number of piles that can be tested:
← Scroll to see the full table →
| Test method / standard | What it measures and key features |
|---|---|
| Static Load Test (ASTM D1143) | Load capacity with real load; most accurate and the reference standard, but slow and costly |
| Dynamic Load Test — PDA (ASTM D4945) | Load capacity by high-strain impact; fast, economical, can test many piles |
| Seismic / Low Strain (DPT 1551-51 · ASTM D5882-16, withdrawn in 2025) | Integrity and length only, by low-strain impact; does not assess load capacity |
Typically a Static Load Test is used on sample piles to confirm capacity, and then a Dynamic Load Test (PDA) is used to check a large number of piles. Read an in-depth comparison at Dynamic vs Static Load Test: Which Should You Choose?, see "integrity" testing at Seismic Test (Low Strain), or see SPN's full range of pile testing services
This article is provided as engineering knowledge. The choice of reaction system, loading method, test load and interpretation criteria should follow the project specification and the judgment of a licensed engineer.