Frequently asked questions about geotechnical instrumentation
What is geotechnical instrumentation?
Geotechnical instrumentation is the installation of instruments that measure how soil and structures behave, including settlement, pore water pressure and lateral movement. The data confirms the design, gives early warning and supports EIA reporting.
What is a settlement plate used for?
A settlement plate measures settlement of the original ground under fill. It is a 60×60 cm steel plate placed on the original ground before filling, with a steel rod extended above the fill surface. It is used under embankments, roads and preloading projects on soft clay, and is levelled with an auto level at every reading.
What is the difference between a piezometer and an observation well?
A piezometer measures pore water pressure at a specific depth, while an observation well measures the overall groundwater level of a soil layer. Piezometers are either standpipe (lower cost) or vibrating wire (higher accuracy, datalogger-ready). Observation wells suit long-term monitoring and EIA work.
How does an inclinometer work?
An inclinometer measures tilt and lateral movement with depth. A probe is lowered through ABS casing installed in the ground and records the tilt every 0.5 m. The readings are used to calculate a displacement profile over the whole casing, giving warning before failure.
Is a vibrating wire piezometer better than a standpipe piezometer?
A vibrating wire piezometer is more accurate, responds faster and can be read continuously through a datalogger with automatic alerts. A standpipe piezometer costs less but is normally read by hand (a pressure transducer can be added for automatic reading). In clay it responds more slowly, because water must flow in and out of the pipe (time lag).
How does a datalogger work, and can it send alerts?
Yes. A datalogger records readings automatically at the set interval and sends the data over 4G or WiFi to a cloud server. Thresholds can be set so that SMS, LINE or email alerts go out automatically when a value exceeds a safe limit, and several instrument types can be connected at once.
Should instruments be installed before or during construction?
Instruments should be installed before construction starts, so baseline readings of the soil and groundwater can be taken under normal conditions. Monitoring then continues during and after construction, so changes can be compared and project decisions are based on data.
Which standards does SPN follow for instrumentation?
Inclinometer monitoring follows ASTM D6230, and vibrating wire piezometers are checked before installation to ASTM D7764, together with the instrument manufacturer's manuals. Instrumented piles are load tested to ASTM D1143. Work is supervised and results are certified by a licensed civil engineer (Council of Engineers Thailand licence).
What criteria are used for construction vibration monitoring?
Vibration is assessed against National Environment Board Notification No. 37 (B.E. 2553), or DIN 4150-3 / BS 7385-2 when the project specification requires it. SPN installs triaxial geophones on the foundations or structure of neighbouring buildings and records peak particle velocity (PPV, mm/s) together with frequency.