Hydraulic jack and dial gauges measuring settlement beneath a kentledge platform during a Static Load Test on a 0.40 m square pile, on site by the SPN team
A Static Load Test applies real load to the pile head in increments through a hydraulic jack, while dial gauges record the settlement to plot the Load-Settlement curve (Photo: SPN Soil Engineering)

Which curves are used to read Static Load Test results?

Static Load Test results are read mainly from the Load-Settlement curve, supported by the Time-Settlement curve. Both come from applying real load to the pile head in increments up to the maximum test load in the spec, which is typically 2–3 times the design load, depending on each project's requirements.

Each load increment is held until the settlement meets the stability criterion, and the readings are recorded with dial gauges before the next increment is added. Once the maximum load is reached, the load is removed in steps and the rebound is measured. Testing and interpretation follow ASTM D1143/D1143M-20e1 and DPT 1251 (the static pile load test standard of the Department of Public Works and Town & Country Planning).

The result is a Load–Settlement–Time dataset, which is plotted as 2 main curves:

  1. Load-Settlement curve — load on the horizontal axis, settlement on the vertical axis; used for the main interpretation
  2. Time-Settlement curve — shows settlement versus time at each load increment; used to confirm that settlement has truly stabilized before more load is added
Actual Load-Settlement curve from an SPN Static Load Test report on a 400 mm square pile, showing the loading branch up to approximately 185 t and the unloading branch with clear rebound
Load-Settlement curve from an actual SPN test report (SQ-400 pile) — the upper line is the incremental loading branch, the lower line is the unloading branch. The recovered portion is the elastic rebound and the remainder is the residual settlement. A smooth, continuous curve with no steep drop = no failure observed

(For the test method and site preparation basics, see What is a Static Pile Load Test, and for an overview of all test methods, see The complete guide to pile testing methods)

What should you check on the Load-Settlement curve?

Reading Static Load Test results means checking 3 things together — gross settlement, residual settlement and the curve shape — not drawing a conclusion from a single settlement number. The table below summarizes what each one measures, the usual criterion and what it means when the criterion is exceeded.

← Scroll to see the full table →

Summary of the 3 things to check when reading Static Load Test results
ItemWhat is measuredTypical criterionMeaning if exceeded / abnormal
1. Gross settlement
Gross Settlement
Maximum pile-head settlement when the load reaches its maximum (mm)Project-specific — the spec sets the allowable value based on pile size and test loadGross settlement above the spec limit = test failed
2. Residual settlement
Residual Settlement
Permanent settlement remaining after all load is removed (mm)Project-specific — a good pile should rebound a lot and leave little permanent settlementAbnormally large permanent pile penetration; the cause must be investigated before the result is accepted
3. Curve shape
Curve Shape
Slope and continuity of the Load-Settlement curve at each load incrementMust not plunge steeply before the maximum test load is reachedNear-vertical drop = pile failure (geotechnical failure)

1. Gross settlement at maximum load (Gross Settlement)

This is the maximum settlement when the load reaches its maximum. The project spec sets a clear allowable value; the figure varies by project and pile size, so always check your own spec. If the gross settlement exceeds the limit = failed.

2. Residual settlement after unloading (Residual Settlement)

After all load is removed, the pile head recovers partly (elastic rebound); the part that does not recover is the permanent settlement. This value tells you how far the pile has actually "sunk". A good pile should recover a lot and leave little permanent settlement.

3. Curve shape — signs of failure

The shape of the curve reflects how the pile carries load. The common patterns are:

← Scroll to see the full table →

Load-Settlement curve shapes and what they mean
Load-Settlement curve patternPossible meaning
Gentle slope, gradual curvature; settlement increases slowly and stabilizes at every load incrementThe pile carries load well and is still far from its ultimate capacity
The curve clearly steepens toward the endThe pile is approaching its ultimate capacity; check the criteria as well
Near-vertical drop (plunging) — a small load increase causes continuous settlement that does not stopPile failure (geotechnical failure); the soil can no longer carry the load
Abnormal settlement jump at one load incrementPossible problem with the pile structure or the test system; must be investigated

The figure below draws all 4 patterns from the table so you can see their actual shapes, with what each one means and what to do next. Note the vertical dashed line, which represents the maximum test load: curve C plunges before reaching this line, so the pile is considered to have failed.

Guide to reading four common Load–Settlement curve shapes from a Static Load Test, with their meaning and next steps (conceptual example) A four-panel diagram arranged in two rows and two columns, a conceptual example using assumed values, not actual test results. Each panel has a small Load–Settlement chart with applied load on the horizontal axis and settlement increasing downward on the vertical axis; dots on the line are the end values of each load increment, and the vertical dashed line is the maximum test load. To the right of each chart is what that curve means and what to do next. Panel A: the curve bends gradually and settlement stabilizes at every increment up to the maximum test load; on unloading the line rebounds, leaving little residual settlement. It means the pile carries load well and is still far from its ultimate capacity; compare the gross and residual settlement with the allowable values in the spec. Panel B: the curve clearly steepens toward the end. It means the pile is approaching its ultimate capacity; use the Davisson criterion to estimate the ultimate capacity as well, shown as a red dashed line the curve is heading toward. Panel C: the curve drops almost vertically, or plunges, before the maximum test load; a small load increase causes continuous settlement that does not stop. It means the pile has failed because the soil can no longer carry the load; the test is considered failed and the cause must be investigated with the design engineer. Panel D: settlement jumps abnormally at one load increment and then resumes increasing slowly. It means there may be a problem with the pile structure or the test system, which must be checked before the result is accepted. The bottom strip summarizes the three things to check together every time: gross settlement at the maximum test load within the spec, residual settlement after full unloading within the spec, and no plunging before the maximum test load. Reading Load–Settlement curves: 4 common shapes Not to scale Conceptual example (assumed values) · dot = end of each load step · vertical dashed line = max. test load A Gradual curve, stable at every step Load → ← Settles Low residual after unloading Means Carries load well Far from ultimate Next step Compare gross/residual with spec limits B Clearly steepens toward the end Load → ← Settles Davisson line Steepening Means Nearing ultimate Check criteria first Next step Use Davisson to estimate ultimate C Near-vertical drop (plunging) Load → ← Settles Plunges before max. test load Means Pile failure Soil can't carry load Next step Failed; find the cause with the design engineer D Abnormal jump at one step Load → ← Settles Sudden jump at one step Means Possible pile defect or test-system issue Next step Check pile & system before accepting 1 Gross ≤ spec at max. test load 2 Residual ≤ spec after full unloading 3 No plunging before max. load
Guide to 4 Load-Settlement curve shapes: A gradual curve with good rebound; B steepens toward the end, so the Davisson criterion is also needed; C plunges before the maximum test load = pile failure; D a settlement jump at a single increment = check the pile and the test system — a conceptual example with assumed values, not actual test results. The criteria actually applied follow the project spec

If your curve plunges or settles beyond the limit, see the investigation sequence and remedial options in Static Load Test failed: what to do

Kentledge reaction system and hydraulic jack loading the pile head during a Static Load Test on site
A kentledge system uses a stack of dead weight as the reaction so the hydraulic jack can load the pile head in increments (Photo: SPN Soil Engineering)

What is the Davisson Offset criterion and how is it used to find the ultimate capacity?

The Davisson Offset Method is the most widely used graphical criterion for estimating the ultimate capacity from a Load-Settlement curve. A line is drawn parallel to the PL/AE elastic compression line, shifted down by 4 + D/120 mm; the point where this line intersects the curve is the ultimate capacity.

This criterion is needed when the curve shows no clear failure, which is the case most of the time, because tests usually stop at 2–3 times the design load. There are 3 steps:

  1. Draw the Elastic Line — the elastic compression line of the pile itself, calculated from PL/AE = (load × length) ÷ (cross-sectional area × elastic modulus of the pile material)
  2. Shift that line down in parallel by Offset = 4 mm + (pile diameter D ÷ 120), with D and the result in millimeters (4 mm is the SI rounding of 0.15 in = 3.81 mm in Davisson's original)
  3. The point where the offset line intersects the Load-Settlement curve is the ultimate capacity by the Davisson criterion
🧮 Example offset calculation

From SPN's actual test result in the next figure — square pile SQ-400 (400 mm) → Offset = 4 + (400 ÷ 120) ≈ 7.3 mm, matching the position of the Davisson line drawn on the chart. The larger the pile, the further the offset line shifts down; for example, a 600 mm bored pile gives ≈ 9.0 mm.

Example Davisson Offset analysis from an actual SPN test result on an SQ-400 pile, showing the elastic line, the offset line of 4 mm plus D divided by 120, and the extrapolated curve intersecting at Qu of approximately 250 t
Davisson Offset analysis of an actual SPN test result (SQ-400 pile → Offset = 4 + 400/120 ≈ 7.3 mm) — the measured curve stops at ~185 t without crossing the Davisson line. Qu ≈ 250 t is obtained by extrapolating the curve (purple dashed line), so it is an estimate, not a value actually reached; the elastic line in this example is estimated from the initial slope of the curve
📐 Reading the Davisson line

If the curve runs to the end of the test without crossing the Davisson line at all, the ultimate capacity of the pile is higher than the maximum test load, which is a good result — the pile has more reserve capacity than the load tested.

Besides Davisson, some projects use other criteria such as the Chin Method, Mazurkiewicz or De Beer; the project spec will state which criterion applies.

Where does the measured settlement come from?

The settlement measured by the dial gauges at the pile head comes from 2 parts: elastic compression of the pile itself and movement of the pile in the soil. These must be separated before drawing conclusions.

  • Elastic compression of the pile (Elastic Compression) — the concrete pile shortens under the applied load, like a very stiff spring. This part recovers when the load is removed and is not a problem; the longer the pile, the larger this part
  • Movement of the pile in the soil (Pile Movement) — the pile actually moves down into the soil; this part tells you how the supporting soil behaves
⚠️ Don't look at gross settlement alone

A long pile with seemingly large gross settlement may simply have high elastic compression due to its length, not because the soil cannot carry the load. That is why reading gross settlement alone is not enough — always separate the components and check the rebound as well.

The 3D view below exaggerates the movement for clarity. The dashed line is the pile position before loading; the orange arrows show that the pile head moves down the most (the value S read by the dial gauge), while the pile toe moves down less (s). The difference is the compression of the pile itself — which is why the Davisson criterion starts from the PL/AE line before applying the offset.

3D model showing that the settlement measured at the pile head in a Static Load Test consists of elastic compression of the pile and movement of the pile in the soil, and why the Davisson criterion starts from the PL/AE line A conceptual 3D view of a soil block cut through the pile centerline, showing the pile section through soft clay, stiff clay and sand layers. Load P from the jack presses on the pile head. The blue dashed line is the pile position before loading, and the concrete pile shows its position under load, with the movement exaggerated. The pile head moves down the most, equal to the value S read by the dial gauge on the reference beam, while the pile toe moves down less, equal to s, which is the movement of the pile in the soil. Orange arrows beside the pile show that each point along its length moves down by a different amount, largest at the head and decreasing to the toe. Green arrows show the soil resistance around the pile and at the toe. The difference between S and s is the elastic compression of the pile itself, which depends on load P, length L, cross-sectional area A and elastic modulus E of the pile material. The box on the right summarizes that the pile-head settlement equals elastic compression plus movement in the soil; elastic compression recovers on unloading and grows with pile length, while movement in the soil reflects the behavior of the supporting soil. The Davisson criterion therefore starts from the elastic line calculated from PL/AE and shifts it down in parallel by a further 4 millimeters plus D divided by 120; an SQ-400 pile gives about 7.3 millimeters and a 600 millimeter bored pile about 9.0 millimeters, with a warning not to conclude from the gross settlement figure alone but to check the rebound as well. 3D model: head settlement = pile compression + movement in soil Not to scale Load P from hydraulic jack Before loading Dashed S at pile head Dial gauge reading L = pile length Pile A, E A = section area E = elastic modulus Head moves most Arrows = movement Pile shortens δ = S − s Pile toe Soil movement = s Green arrows = soil resistance on shaft & toe Section: soft clay / stiff clay / sand · movement exaggerated Head settlement has 2 parts S head settlement (measured) = δ pile compression s in soil δ Elastic pile compression Recovers on unloading Longer pile, larger δ s Pile movement in soil Pile actually sinks Reflects bearing soil Davisson criterion Start from elastic line = PL/AE Shift down 4 + D/120 mm SQ-400 ≈ 7.3 mm 600 mm bored pile ≈ 9.0 mm Don't judge by gross alone Long pile, large gross: may be δ not soil overload Check the rebound as well Conceptual, not measured data
3D model: pile-head settlement (S) = elastic compression of the pile (δ, estimated from PL/AE) + movement of the pile in the soil (s). The Davisson criterion therefore starts from the PL/AE line and shifts it down by a further 4 + D/120 mm (SQ-400 ≈ 7.3 mm) — a conceptual view with exaggerated movement, not measured values. Not to scale

Did the Static Load Test pass? A 6-point checklist

A pile passes when the test result meets all 6 points below. Check them in this order:

  1. Did the test load reach the maximum in the spec (e.g. 2 times the design load)?
  2. Is the gross settlement at maximum load ≤ the spec limit?
  3. Is the residual settlement after unloading ≤ the spec limit?
  4. The curve shows no plunging before the maximum load
  5. The curve does not cross the Davisson line (or, if it does, the resulting ultimate capacity ≥ the value required by the spec)
  6. The Time-Settlement curve at each load increment shows settlement stabilized before more load was added

Meeting all points = the pile passes the test criteria. However, the official conclusion must be made by an engineer, and final acceptance rests with the project's design engineer. To check whether a full report contains all the required information, see the pile test report checklist

🔗 Read more

Compare with how dynamic tests are interpreted in How to read PDA test results · Not sure whether to use a static or dynamic test? See Dynamic vs Static: which to choose · For budget and schedule planning, see Pile testing prices 2026 and How many days after casting can a pile be tested

Summary

Reading Static Load Test results requires checking 3 things together: gross settlement against the spec limit, residual settlement after unloading, and a curve shape that does not plunge. The ultimate capacity is estimated with the Davisson Offset criterion (the PL/AE line shifted down by 4 + D/120 mm), and you must distinguish which part of the settlement is elastic compression of the pile itself, which is not a problem.

A good report must present the Load-Settlement curve, the Time-Settlement curve and the analysis by the criteria required in the spec in full, with the conclusion made and certified by an engineer.

SPN Soil Engineering provides pile testing services including Static Load Tests to ASTM D1143/D1143M-20e1 and DPT 1251 nationwide across all 77 provinces of Thailand, with Load-Settlement curve reports and analysis by the criteria in the spec. Reports are certified by a licensed civil engineer registered with the Council of Engineers Thailand (COE) and can be submitted to the relevant authorities for building permit applications.