Why do piles deviate from their design position?

Deviation of piles from their design position occurs on almost every foundation project and does not always mean the work was faulty. Common causes include:

  • Underground obstructions — old concrete debris, tree stumps, boulders or buried old foundations deflect the pile during driving
  • Sloping or variable soil layers — the pile tip slides along a sloping hard layer, especially where soil conditions change quickly
  • Control of the starting position — the setting-out peg or pile verticality is off from the start
  • Soil displacement from driving adjacent piles — especially in closely spaced pile groups in soft clay, where driving later piles can push earlier ones out of position

Because deviation cannot be avoided entirely, the new law is not written as "no deviation allowed". It takes an approach closer to site reality: it requires the design to allow for deviation in advance.

Driven piles on an actual construction site, where each pile head position must be surveyed against its design position
Driven piles on an actual site — the head position of every pile must be surveyed against the design layout to check deviation (image: SPN Soil Engineering)

What deviation criteria does the law set? (75 mm / 50 mm / 10%)

The Ministerial Regulation Prescribing Building Foundations and Ground Supporting Buildings B.E. 2566 (2023), in force since 28 February 2024 (see the full overview in our plain-language summary of the 2023 Foundation Ministerial Regulation), sets clear numerical criteria for pile deviation in Clause 28:

← Scroll to see the full table →

IssueCriteria under the 2023 Ministerial Regulation (Clause 28)
Deviation from center of each pileThe building structure above the foundation must be designed to accommodate at least 75 mm
Piles arranged in a single rowDesigned to accommodate a deviation of at least 50 mm
Effect of deviation on each pileMust not cause any pile to carry more than its design load by over 10 percent

The clever part of this requirement is that it does not prohibit pile deviation, but requires the design to allow for deviation in advance. In practice, if the deviation is within what the design allows and the engineer has verified that no pile carries more than 10 percent above its design load, work can proceed. If the deviation is larger, the inspection and remediation process required by the Ministerial Regulation applies.

The mechanism behind the check: when piles in a group deviate unequally, the centroid of the pile group is offset from the center of the column by a distance e. The column load P then produces a moment M = P × e, so some piles carry more load and others less. The 10% criterion is therefore checked on the most heavily loaded pile, not on the group average.

📚 A shift in perspective

Before this Ministerial Regulation, deviation criteria were usually project-specific (spec) requirements that could be negotiated on site. Now the minimum criteria have been raised to law — so when a pile deviates, the question is no longer "is deviation allowed?" but "how much has it deviated, has it been measured, and has the engineer checked the effects?"

The figure below shows a four-pile foundation layout with unequal deviations, and hypothetical values of the force in each pile for small and large deviation, compared with the +10% limit line.

2D diagram of off-center piles in a foundation layout and the effect on the force in each pile compared with the 10 percent criterion Conceptual 2D diagram. The left panel is a plan view of a four-pile foundation. Dashed circles are the design positions, blue circles are the 75 millimeter range the design must accommodate, solid circles are the actual surveyed positions, and arrows show the direction of deviation. One pile deviates outside its circle and is shown in red. The centroid of the pile group is offset from the column center by a distance e, producing a moment P times e. The lower left corner shows piles arranged in a single row under a wall, where the 50 millimeter criterion applies. The right panel is a bar chart of hypothetical forces in the four piles compared with 100 percent of the design value. With small deviation the maximum force is 104 percent and passes; with large deviation the maximum is 114 percent, above the 110 percent line, so the design engineer must check and specify a fix. The bottom row summarizes the Clause 28 criteria. 2D diagram: off-center piles → pile forces change Not to scale Foundation plan (top view) Deviation exaggerated · hypothetical Column e Design position 75 mm allowance Actual position Beyond allowance e = pile group centroid offset → M = P × e Force in each pile (hypothetical) 80% 90% 100% 110% 120% +10% limit P1 P2 P3 P4 Small dev. Max 104% P1 P2 P3 P4 Large dev. Max 114% 100% = design force per pile 1 Design for deviation of at least 75 mm (Cl. 28) 2 Piles in a row at least 50 mm 3 Force in any pile may rise max. 10%
2D diagram — left: foundation plan from above; dashed circles are design positions, blue circles are the 75 mm allowance (exaggerated for clarity), solid circles are actual positions; the red pile deviates beyond the allowance. The pile group centroid is offset by e, producing M = P × e. Right: hypothetical pile forces; with small deviation the maximum is 104% (pass), with large deviation the maximum is 114%, above the 110% line (image: SPN Soil Engineering)

Found deviated piles on site? 4 steps to take

Step 1 — Survey the actual position of every pile

Measure the coordinates of each pile head against its design position (as-built survey) and document the distance and direction of deviation for each pile. Never judge by eye, because the legal criteria are in millimeters. Every following decision must be based on this measured data.

Step 2 — Send the data to the design engineer for checking

The engineer will analyze the redistribution of load in the pile group, check whether any pile carries more than 10 percent above its design load, and whether the additional moment on the pile cap and column is still within what the structure can carry. This step is the direct responsibility of the project's design engineer.

Step 3 — Check the integrity of piles with large deviation

Piles with large deviation usually raise the question of whether the pile is "broken, cracked or bent" underground. The fastest and most economical screening tool is the Seismic Integrity Test (DPT 1551-51 — ASTM D5882-16 was withdrawn in 2025), which checks the continuity of the pile shaft non-destructively in just a few minutes per pile. If the load capacity of a suspect pile needs to be confirmed, it can be followed by a Dynamic Load Test (PDA) per DPT 1252-51 — see a comparison of pile test methods in Dynamic vs Static Load Test, and if a pile fails the seismic test, see the follow-up checks and remedies in Pile failed the seismic test: what next?

Step 4 — Act on the analysis results

If the analysis shows the criteria are exceeded, the remedy is at the discretion of the design engineer, for example enlarging the pile cap, adding supplementary piles or adjusting the column position — this article gives an overview for understanding only and is not remedial advice for any particular project, because each site has different loads, soil conditions and foundation types.

The 3D model below combines the four steps in a single site view, from surveying actual positions with a total station to checking the integrity of the pile that deviates beyond the allowance.

3D model of checking off-center piles on site, from surveying actual positions to integrity testing Conceptual 3D view of a block of soil cut away to show a section. On the ground surface is a group of six piles for one pile cap. Dashed lines are the design grid lines, and blue ellipses are the 75 millimeter allowance around the design positions. Most pile heads are inside their ellipses; one pile head deviates outside and is shown in red. The section shows the front row of piles, with the deviated pile inclined from vertical. At the front left is a total station on a tripod sighting a target on a pile head to carry out an as-built survey of every pile. Next to the red pile a technician performs a Seismic Integrity Test to check integrity. The right panel lists the four steps: survey the actual position of every pile; send to the design engineer to analyze pile group forces so none exceeds ten percent; check the integrity or capacity of suspect piles; and remedy as specified by the engineer. 3D model: deviated piles found on site — what to do Not to scale 1 As-built Survey Survey every pile head 2 75 mm allowance around design position 3 Beyond allowance Seismic test / analysis Section: deviated piles often tilt from vertical — integrity check required 4 steps when piles deviate 1 Survey actual position of all As-built survey, not by eye 2 Send to design engineer Pile group force analysis ≤ +10% 3 Check suspect piles Integrity DPT 1551-51 · PDA 4 Fix per analysis Larger cap · add piles · shift col. Remedy is at the discretion of the project design engineer Conceptual view, not to scale
3D model — ① a total station surveys the head coordinates of every pile (as-built survey) ② blue rings are the 75 mm allowance around the design positions on the grid lines ③ the red pile deviates beyond the allowance and tilts from vertical in the section, so its integrity is checked and the engineer analyzes the effects. The right panel shows the four steps. Conceptual image (image: SPN Soil Engineering)

How can pile deviation be prevented from the start?

  • Carry out adequate soil investigation — knowing in advance where hard layers slope or obstructions lie helps plan driving and choose the right pile type (see guidance on the right number and depth of boreholes)
  • Control pile driving/boring with periodic position surveys — check coordinates as work progresses rather than measuring once at the end, because problems found early are cheaper to fix
  • Test pile integrity with comprehensive seismic testing — especially in zones with hard driving, obstructions or unusual deviation

Is checking deviated piles expensive?

Compared with the risk of continuing construction on problem piles, the cost of testing is very low:

  • Seismic Integrity Test — about THB 100–150/pile, suitable for screening large numbers of piles
  • Dynamic Load Test (PDA) — from about THB 5,500/pile, used to confirm the load capacity of suspect piles

Both are starting prices; the actual cost depends on the number and size of piles. These prices do not include travel and equipment mobilization costs, which are charged based on the distance to the site.

Summary: a deviated pile is not the end — if it is measured and checked by an engineer

The 2023 Foundation Ministerial Regulation turns pile deviation from an on-site negotiation into clear numerical criteria: the design must allow for 75 mm of deviation (50 mm for piles in a single row), and the effect must not cause any pile to carry more than 10 percent above its design load. When piles deviate, measure them, have the engineer analyze, and check integrity — never judge by eye — and let the design engineer decide whether they pass or need remedial work.

📌 Disclaimer

This article summarizes the Ministerial Regulation for general understanding only. It is not legal or engineering advice for any specific project. For practical use, refer to the official text of the Ministerial Regulation as published in the Royal Gazette and consult the licensed engineer for your project.