What Is a Temporary Earth Retaining System, and How Does It Differ from a Permanent Retaining Wall?

A temporary earth retaining system is a structure installed to support the soil around an excavation so it does not collapse during construction, such as sheet piles, a contiguous pile wall (a continuous row of bored piles) or a sloped excavation (cut slope). It is used only during construction; once the underground structure is complete and backfilled, the retaining system has done its job.

It differs from a permanent retaining wall in 2 respects: service life and design criteria.

  • Factor of Safety: temporary works resist earth pressure only for a short period, so a lower F.S. than for permanent works can be used (see the F.S. criteria for permanent works in Retaining Wall Safety Factors Under Thai Law)
  • Monitoring during excavation: monitoring of actual behavior during excavation must always go alongside, because the highest risk occurs while the excavation is being opened up.

What Was the Brief for This Project?

📍 Project details

Design of a temporary earth retaining system for a 4.00 m deep excavation within a construction project in Khon Kaen Province — SPN Soil Engineering was responsible for the design, the stability checks and the movement-monitoring criteria during construction.

The brief had 2 requirements. First, the excavation lay within a project site where other construction was under way, so lateral ground movement had to be kept within safe limits throughout excavation. Second, a sump pit had to be opened inside the excavation to drain water during construction.

What Were the Site Soil Conditions, and Which Design Parameters Were Used?

The soil profile has 3 main layers: clayey sand, hard clay and sandstone. Data from the soil investigation were converted into design parameters for the Mohr-Coulomb model as follows:

← Scroll to see the full table →

Soil layerUnit Weight (t/m³)c′ / Su (t/m²)φ′ (°)
Medium Dense Clayey Sand1.8030
Hard Clay2.0100
Sandstone2.41533

The analysis includes a surface surcharge of 2.0 t/m² to allow for machinery and construction materials around the edge of the excavation. This step shows that thorough soil investigation (see the criteria for number of boreholes and depth) is the starting point of accurate earth retaining design.

Which Earth Retaining System Was Chosen?

The designer chose a combined system of 2 parts to suit the site: a bored pile wall on the sides where space is limited, and a cut slope on the sides with enough room.

  • Contiguous Pile Wall: reinforced concrete bored piles, Dia 0.35 m, in a continuous row at 0.40 m spacing (gap between piles no more than 0.05 m), with a 0.65×0.60 m cap beam; used on sides where space is limited or close to existing structures
  • Cut Slope 1:1: a 45° sloped excavation on sides with enough room, covered with 10 cm of lean concrete to protect the slope face from erosion
Conceptual section of the temporary earth retaining system for a 4.00 m deep excavation: a 1:1 cut slope on one side and a contiguous pile wall on the other, with the excavation sequence and inclinometer Section of a 4.00 m deep excavation. The left side is excavated to a 1:1 slope, covered with 10 cm of lean concrete; the factor of safety of the cut slope is 5.092. The right side is a contiguous bored pile wall, 0.35 m diameter at 0.40 m spacing, with a 0.65×0.60 m cap beam. Horizontal dashed lines show the excavation levels: stage 1 at −1.00 m, stage 2 at −2.00 m and the base at −4.00 m. A sump pit sits at the base. Behind the wall, an inclinometer casing measures lateral movement, and a surface surcharge of 2.0 t/m² is applied. Soil layers from top to bottom are medium dense clayey sand, hard clay and sandstone. The bottom band shows the 6-stage construction sequence with F.S. values of 11.32 at −1.00 m, 7.51 at −2.00 m, 4.57 at −4.00 m and 4.57 when the sump pit is opened, and maximum allowable movements of 1.8, 3.4, 5.9 and 5.7 mm respectively. Section (2D): 4.00 m excavation · Cut Slope + Contiguous Pile Wall Conceptual view · Not to scale Surcharge 2.0 t/m² Depth 4.00 m Phase 3 · −1.00 m Phase 4 · −2.00 m Phase 5 · −4.00 m base Cut Slope 1:1 (45°) Lean Concrete 10 cm thick F.S. = 5.092 Contiguous Pile Wall Bored pile Dia 0.35 m @ 0.40 m Cap Beam 0.65×0.60 m Inclinometer Lateral movement vs Trigger Level each Phase Phase 6 · Sump Pit Clayey sand γ 1.8 t/m³ · φ′ 30° Hard Clay γ 2.0 t/m³ · Su 10 t/m² Sandstone γ 2.4 t/m³ · c′ 15 t/m² · φ′ 33° Layer depths not shown 6-stage sequence · temporary works F.S. ≥ 1.30 1 Install retaining piles along the pit edge 2 Initial reading Install Inclinometer 3 Dig to −1.00 m F.S. 11.32 4 Dig to −2.00 m F.S. 7.51 5 Dig to −4.00 m F.S. 4.57 · base 6 Open Sump Pit F.S. 4.57 Max. allowable movement Phase 3 1.8 mm Phase 4 3.4 mm Phase 5 5.9 mm Phase 6 5.7 mm Alarm 70% · Alert 80% · Action 90% of design value in each Phase
Conceptual section of the 4.00 m deep excavation — 1:1 cut slope on one side and contiguous pile wall on the other, with the excavation level of each phase, F.S. values and maximum allowable movements. Figures come from the project design results; the drawing does not show soil layer depths and is not to scale (Image: SPN Soil Engineering)
Plan and section of a contiguous pile wall, Dia 0.35 m at 0.40 m spacing, for a 4 m deep excavation, drawing GE-01
Drawing GE-01 — plan and section of the contiguous pile wall, Dia 0.35 m @ 0.40 m, combined with a 1:1 cut slope for a 4.00 m deep excavation (Drawing: SPN Soil Engineering)
Detail drawing of the retaining piles and cap beam with a 3D view of the contiguous pile wall, drawing GE-02
Drawing GE-02 — reinforcement details of the retaining piles and cap beam, and a 3D view of the contiguous pile wall system (Drawing: SPN Soil Engineering)

How Was Stability Analyzed with FEM?

The analysis used the finite element method (FEM) to model the actual construction sequence (staged construction) in 6 stages, to see ground movement and stability at each step of the excavation — not just the final condition.

← Scroll to see the full table →

PhaseConstruction stageDetails
1Install Bored Pile WallInstall retaining bored piles along the excavation edge
2Initial Inclinometer ReadingInstall inclinometer casing and take initial baseline readings
31st ExcavationExcavation stage 1 to −1.00 m, with monitoring
42nd ExcavationExcavation stage 2 to −2.00 m, with monitoring
5Final ExcavationExcavate to the base at −4.00 m; prepare to build the underground structure
6Open Sump PitOpen a sump pit inside the excavation to drain water during construction
FEM result: horizontal displacement ux, retaining bored pile installation stage (Install Bore Pile)
FEM result: horizontal displacement (total displacements ux), retaining bored pile installation stage (Image: SPN Soil Engineering)
FEM result: vertical displacement uy, retaining bored pile installation stage (Install Bore Pile)
FEM result: vertical displacement (total displacements uy), retaining bored pile installation stage (Image: SPN Soil Engineering)
FEM result: horizontal displacement ux, Open Sump Pit stage at 4 m excavation depth
FEM result: horizontal displacement (ux), final stage Open Sump Pit — the most critical step of the excavation (Image: SPN Soil Engineering)
FEM result: vertical displacement uy, Open Sump Pit stage at 4 m excavation depth
FEM result: vertical displacement (uy), Open Sump Pit stage (Image: SPN Soil Engineering)

What Were the Factors of Safety (F.S.) at Each Stage?

F.S. ranges from 4.57 to 11.32 and decreases with excavation depth, because lateral earth pressure and stress relief increase. However, every stage remains above the minimum criterion for temporary works, F.S. ≥ 1.30, set by the designer. This depends on each project's specification.

← Scroll to see the full table →

Analysis CaseExcavation stageFactor of Safety
FS 11st Excavation (−1.00 m)11.32
FS 22nd Excavation (−2.00 m)7.51
FS 33rd Excavation (−4.00 m)4.57
FS 4Open Sump Pit / Final Stage4.57

How Stable Is the Cut Slope?

The cut slope is sufficiently stable throughout construction. On the side excavated to a 1:1 slope, slope stability was checked separately using the limit equilibrium method, giving a Factor of Safety = 5.092, well above the criterion for temporary works (see the calculation principles in Slope Stability and Factor of Safety)

Stability analysis of a 1:1 cut slope, 4 m deep, giving a factor of safety of 5.092
Stability analysis of the 1:1 cut slope, 4 m deep — Factor of Safety = 5.092, with Mohr-Coulomb parameters for the 3 soil layers (Image: SPN Soil Engineering)

How Were the Retaining Piles Reinforced?

The bending moments, shear forces and axial forces from the FEM were used to check the strength of the piles' reinforced concrete section, resulting in the following reinforcement details:

  • Bored pile Dia 0.35 m: longitudinal bars 6-DB16 (SD40, fy = 4,000 ksc) + spiral ties RB9 @ 0.15 m, concrete cover 5 cm
  • Cap Beam 0.65×0.60 m: longitudinal bars 4-DB20 top and bottom + stirrups RB9 @ 0.125 m
  • Concrete strength: the structure uses fc′ = 280 ksc (section checked at a guaranteed strength of 240 ksc)

The section checks passed every criterion, with capacity-to-demand ratios Sn/U = 1.76, Mn/Mu = 1.90 and Pn/Pu = 4.89 (all must exceed 1.00).

Interaction diagram checking the section capacity of a Dia 0.35 m bored pile with 6-DB16 reinforcement
Interaction diagram checking the section capacity of the Dia 0.35 m bored pile with 6-DB16 reinforcement — the actual force points lie inside the section capacity envelope (Image: SPN Soil Engineering)

Why Monitor with an Inclinometer During Excavation?

Because the FEM results are only a prediction — reality must be proven by measurement. This project therefore required installation of an inclinometer to measure lateral ground movement and compare it against 3 control levels (trigger levels) calculated as percentages of the design movement in each phase (see how the instrument works in What Is an Inclinometer, and other instruments used for this kind of work in 10 Types of Geotechnical Instruments)

← Scroll to see the full table →

Trigger LevelPhase 3
(−1 m)
Phase 4
(−2 m)
Phase 5
(−4 m)
Phase 6
(Sump Pit)
Alarm (70%) — notify the designer, keep watch1.3 mm2.4 mm4.1 mm4.0 mm
Alert (80%) — review procedures, increase monitoring frequency1.4 mm2.7 mm4.7 mm4.6 mm
Action (90%) — stop/slow work, define corrective measures1.6 mm3.1 mm5.3 mm5.1 mm
Maximum — maximum allowable value1.8 mm3.4 mm5.9 mm5.7 mm

A trigger level system like this lets everyone know in advance what to do at which reading, without waiting for damage to occur before deciding. It is at the heart of modern risk management for deep excavations.

Conceptual 3D model of one corner of a 4 m deep excavation: cut slope, contiguous pile wall, sump pit and inclinometer A 3D cutaway showing one corner of a 4.00 m deep excavation. At the back left is a 1:1 cut slope with its surface covered in lean concrete; at the back right is a contiguous bored pile wall, 0.35 m diameter at 0.40 m spacing, with a cap beam on top. Dashed lines on the wall show the excavation levels of stage 1 at −1.00 m and stage 2 at −2.00 m. The base is at −4.00 m, with a sump pit and a standing person for scale. On the ground surface behind the wall, arrows represent a surcharge of 2.0 t/m². The section on the right shows the pile tips embedded below the base, and the inclinometer casing in the soil behind the wall bending toward the excavation, drawn exaggerated. The section shows three soil layers: clayey sand, hard clay and sandstone. The panel on the right explains the three control levels: Alarm at 70 percent, Alert at 80 percent and Action at 90 percent of the design value. 3D model: corner of a 4 m excavation and temporary retaining system Not to scale −1.00 m −2.00 m Base −4.00 m Clayey sand Hard clay Sandst. 1 Contiguous Pile Wall + Cap Beam Bored pile Dia 0.35 m @ 0.40 m 2 Surcharge 2.0 t/m² Machinery · materials at edge 3 Cut Slope 1:1 Lean Concrete 10 cm 4 Sump Pit Phase 6 · drainage during works 5 Inclinometer Bends toward pit (exaggerated) What to do at each reading Trigger Level % of design movement Alarm 70% Notify designer Keep watch Alert 80% Review procedure Monitor more often Action 90% Stop or slow work Define corrective measures Max. allowable value Phase 3 (−1.00 m) 1.8 mm Phase 4 (−2.00 m) 3.4 mm Phase 5 (−4.00 m) 5.9 mm Phase 6 (Sump Pit) 5.7 mm FEM F.S. 4.57–11.32 Above temporary criterion ≥ 1.30 Conceptual · does not show actual layer depths or casing location
Conceptual 3D model of the excavation corner — cut slope, bored pile wall with cap beam, sump pit and inclinometer casing behind the wall (bending drawn exaggerated), with the 3 control levels (Image: SPN Soil Engineering)

Conclusion: Lessons from Designing a Temporary Earth Retaining System

A complete temporary earth retaining design must cover both the design side and control during construction. This case study reflects the standard workflow: soil investigation → choose a retaining system to suit the site → FEM analysis following the construction sequence → structural strength check → set inclinometer monitoring criteria

Note that all figures in this article (pile size, reinforcement spacing, F.S. values and trigger levels) are design results specific to this project, based on the actual soil conditions on site, and cannot be applied directly to other projects. Every deep excavation must be designed afresh by an engineer based on soil investigation data for that site.

SPN Soil Engineering provides the full service, from soil investigation and geotechnical design (earth retaining systems, foundations, slope stability) to installing instruments and monitoring behavior during construction. With more than 20 years of experience, we work nationwide across Thailand. Consult us about your project for free.