SPN engineer using a rebound hammer to estimate concrete compressive strength on a column surface in a building on site
Rebound hammer testing per ASTM C805 has the lowest cost per point of all structural testing methods, so it is often used to survey a wide area before selecting Core Test locations

What determines the price of structural testing?

The price of structural testing (Structural Testing / NDT) is a service fee based on the actual quantity of work, not a price per square meter of building. Every provider prices from the same five components:

  • Mobilization — travel, equipment transport and crew accommodation for provincial sites. This is a fixed cost per trip, independent of the number of points.
  • Unit test cost — charged per point, per member, per specimen or per square meter, depending on the method.
  • Access cost — scaffolding, boom lifts, opening ceilings, removing finishes or working at height.
  • Laboratory testing cost — e.g. compressive strength testing of core specimens.
  • Engineering report cost — analysis of results, conclusions and recommendations, and certification by a licensed engineer.

Because of this price structure, testing 5 points versus 20 points on the same trip does not cost 4 times as much, since mobilization is spread over every point. This is why completing all work in a single trip reduces the total cost the most.

The five price components of structural testing, comparing 5 points vs 20 points in a single trip, and 20 points requiring two site visits A conceptual stacked bar chart, not actual price proportions. The price of a job consists of five parts: mobilization, fixed per trip according to distance; unit test cost, charged per point, per member, per specimen or per square meter; access cost such as scaffolding, boom lifts or ceiling removal; laboratory cost such as compressive strength testing of cores; and the engineering report, in which the engineer analyzes the results and signs. The first bar is five points in a single trip. The second bar is twenty points in a single trip; the total does not rise fourfold because mobilization is spread over all points. The third bar is twenty points requiring two site visits, for example waiting for ceilings to be opened or areas to be closed off, so mobilization is incurred again. The bottom strip shows four ways to reduce cost without reducing result quality: finish in a single trip by preparing the area and opening ceilings in advance; use low-cost methods such as the Rebound Hammer and UPV to survey first and core only at abnormal points; have the original construction drawings ready; and define the question clearly before hiring. Structural testing price: 5 components Not to scale Total quoted price (conceptual) Not actual proportions 5 points One trip 20 points One trip Not 4× Mob. spread over points 20 points 2 site visits Trip 1 Trip 2 Mob. again Await ceiling / closure Mobilization Fixed per trip · by distance Test cost Per point / core / m² Access Scaffold · lift · ceiling Lab cost Core compression Report Analysis · PE signed Cut cost, not quality 1 One trip only Prep site · open ceilings 2 Screen with low-cost NDT Rebound · UPV → targeted cores 3 Have old drawings as-built = less scanning 4 Define the question Don't order every test
The five price components of structural testing — mobilization is a fixed cost per trip, while test costs vary with the number of points

Which methods are low-cost and which are high-cost? Price level by method

The table below compares the relative price level of each structural testing method, where 💰 is the lowest price band and 💰💰💰 the highest. Use it for preliminary budgeting and to choose the method that answers the question you need answered.

← Scroll to see the full table →

Test methodReference standardsWhat it tells youPricing unitPrice level
Rebound Hammer (Schmidt hammer)ASTM C805Approximate surface compressive strength · uniformityPer point💰
Carbonation TestEN 14630 · RILEM CPC-18Carbonation depth that puts the reinforcement at risk of corrosionPer point💰
Cover Meter / Rebar ScanBS 1881-204Location, size and cover of reinforcementPer member💰
UPV (ultrasonic pulse)ASTM C597Concrete uniformity · voids · deep cracksPer point💰
Half-Cell PotentialASTM C876Probability of active reinforcement corrosionPer grid/m²💰💰
GPR concrete scanningASTM D6432Map of reinforcement, embedded conduits and member thicknessPer m²💰💰
Impact EchoASTM C1383Slab thickness and internal voids when only one side is accessiblePer point💰💰
Core Test (core sampling)ASTM C42 · ASTM C39Actual concrete compressive strength usable in calculationsPer specimen💰💰
Pull-Out Test (chemical anchors/studs)ASTM E488Actual pull-out capacity of installed anchorsPer point💰💰
Parallel SeismicASTM D8381/D8381M-21Length of existing piles under a completed buildingPer pile (requires a guide borehole)💰💰💰
Floor Load TestACI 318-19 Chapter 27Proves the floor's load capacity with real loadsPer test area💰💰💰

💰 = low price band · 💰💰 = moderate · 💰💰💰 = high — a comparison between methods for preliminary budgeting only. This is not SPN's service price list and excludes travel and equipment transport, which are charged additionally based on distance to site.

📌 How to read this table in practice

A lower price per point is not always better value, because each method answers a different question — the Rebound Hammer is cheap but gives a surface estimate, while the Core Test costs more but gives a compressive strength that can be used to calculate structural capacity. See more technical differences at NDT vs Core Test: what's the difference?

What factors cause the biggest price differences?

When quotes from several providers differ widely, the gap usually comes from these six factors:

  1. Number of test points and number of trips — the biggest factor. Jobs that need several site visits (e.g. waiting for ceilings to be opened or areas to be closed off) incur mobilization every time.
  2. Distance to site — provincial jobs add travel, equipment transport and crew accommodation.
  3. Difficulty of access — tall columns, slab soffits or points requiring scaffolding/boom lifts multiply the working time per point.
  4. Working hours — work in buildings still in operation often has to be done at night or on holidays, which incurs overtime.
  5. Level of reporting detail — a results-only summary report differs from a report that includes a structural capacity assessment and repair recommendations.
  6. Surface repair after testing — for methods that require drilling, such as the Core Test and Pull-Out Test, state clearly whether patching the holes is included.

Which test package should you choose? 3 packages used in practice

Rather than choosing methods one by one, in practice they are grouped into packages by purpose, which makes the budget easier to control:

← Scroll to see the full table →

Test packageSuited toMethods usually includedOverall price level
Initial screening packageYou want an overview of the building's condition before committing to a detailed investigationVisual condition survey + Rebound Hammer + Cover Meter💰
Pre-purchase / pre-lease packageInspecting a second-hand building or warehouse before signing a contractScreening package + UPV + Core Test at selected points + GPR rebar scanning💰💰
Strength verification packageIncreasing the imposed load, changing the use, or installing new machineryPre-purchase package + Impact Echo + Floor Load Test per ACI 318-19💰💰💰

The price levels above compare test packages; they are not SPN's service prices · The actual scope is set by an engineer after reviewing the drawings and site conditions

The figure below places each test method on a single example building, with the price level of each method — note that the cost does not come from testing alone but also includes access costs such as scaffolding, boom lifts or ceiling removal, which are often left out of the first quote.

3D model of a two-story reinforced concrete building showing the location of each test method, price level, access costs and 3 test packages (conceptual illustration) A conceptual 3D view of a two-story reinforced concrete building frame with six columns, beams and a second-floor slab; the roof is open to show the structure. Six numbered locations are marked. Point one: Rebound Hammer on the surface of the front-left ground-floor column. Point two: UPV with two ultrasonic transducers on opposite faces of the front-middle column. Point three: GPR scanning the reinforcement in a grid on the second-floor slab. Point four: Core Test drilling a concrete core from the second-floor slab. Point five: Floor Load Test with weight bags on the second-floor slab and an arrow showing the applied load. Point six: scaffolding beside the building to reach the upper beams, an additional access cost. The panel on the right lists the methods by number with price levels shown as coins: Rebound Hammer and UPV are in the low band, GPR and Core Test in the moderate band, and Floor Load Test in the high band, while scaffolding, boom lifts and ceiling removal are added access costs. Below the panel, three test packages are summarized: the screening package uses method one with a visual survey and Cover Meter; the pre-purchase or pre-lease package uses methods one to four; and the strength verification package uses methods one to five. Price levels compare methods and are not service prices. 3D model: where to test, by which method, and what drives cost up Not to scale 1 2 3 4 5 6 Conceptual · actual test locations and quantities are set by the engineer after reviewing drawings and site Method · price level 1 Rebound Hammer ฿ 2 UPV (ultrasonic) ฿ 3 GPR rebar scan ฿ ฿ 4 Core Test (coring) ฿ ฿ 5 Floor Load Test ฿ ฿ ฿ 6 Scaffold · lift · ceiling Access cost, on top of testing 3 test packages Screening 1 + visual survey · Cover Meter ฿ Pre-purchase / lease Methods 1–4 ฿ ฿ Strength proof Methods 1–5 (+ Impact Echo) ฿ ฿ ฿ Relative price level, not service prices
Test locations of each method on an example building, price levels and added access costs — the actual test package is set by the engineer after reviewing drawings and the site (conceptual illustration)

If you are inspecting a building before buying or leasing, see the full inspection checklist at Structural inspection before buying or leasing a building or warehouse, and if your question is how much load a floor can carry, see How much load can a factory or warehouse floor carry?

What should a good quotation specify?

Compare the scope before comparing prices. A complete structural testing quotation should specify at least:

  • Test methods with reference standards, e.g. ASTM C805, ASTM C42/C39
  • Number of test points per method, and the locations or members to be tested
  • A clear statement of whether travel, equipment transport, accommodation and access work are included
  • Whether laboratory testing and surface repair after drilling are included
  • Report format, number of copies, and certification by an engineer licensed by the Council of Engineers Thailand (COE)
  • Report delivery time counted from completion of site work
⚠️ Common causes of cost overruns

Items often missing from the first quotation are scaffolding/boom lifts, after-hours work, removal and reinstatement of finishes, and a second site visit when the area is not ready. Ask clearly from the start who is responsible for these.

How can you reduce cost without reducing result quality?

  • Complete all work in a single trip — prepare the area, close it off and open ceilings before the team arrives on site.
  • Screen with low-cost methods first — use the Rebound Hammer and UPV to survey broadly, then core only where results are abnormal.
  • Have the original construction drawings ready — as-built drawings can greatly reduce the number of rebar scanning points.
  • Define the question clearly before hiring — "Can the floor carry the new machinery?" leads to a more cost-effective test package than ordering every method indiscriminately.

How many days does it take to get the report?

1–2
site days
typical test package per building
2–3
days per point
Floor Load Test
7–14
working days
signed report

The durations above are a general guide for sites that are ready. If you need to wait for compressive strength results of specimens or there are many test points, the duration will be longer according to the actual scope.

Which SPN services have clear starting prices?

Some types of work have a more standard scope, so starting prices can be quoted directly:

← Scroll to see the full table →

ServiceApproximate starting priceDetails
Soil investigation for a residential houseTHB 20,000–40,000/job (2–3 boreholes, including basic testing and report)Soil boring prices 2026
Seismic Integrity Test~THB 100–150/pilePile testing prices 2026
Dynamic Load Test (PDA)From ~THB 5,500/pilePile testing prices 2026
Static Load TestTHB 50,000–150,000+/pilePile testing prices 2026

This price excludes travel and equipment mobilization costs, which are charged extra depending on the distance to site.

Concrete core drilling rig mounted on a structural slab to take core specimens for compressive strength testing
The Core Test per ASTM C42/C39 costs more per specimen than indirect methods, but gives an actual compressive strength that can be used as a reference in structural calculations

Summary

Structural testing prices depend on the method, number of points, difficulty of access and distance to site, not on building size. Indirect methods such as the Rebound Hammer and UPV are in the low price band and suit area screening, while the Core Test, Parallel Seismic and Floor Load Test are in the high band because they give strength-related answers that can be relied on. The most effective way to control the budget is to define the question clearly, choose a test package that matches it, and complete the work in a single trip — see an overview of all test methods in the NDT guide for concrete structures, and all services on the Non-Destructive Evaluation (NDE) page.

SPN Soil Engineering provides structural testing and NDT nationwide, with reports certified by civil engineers licensed by the Council of Engineers Thailand (COE). Send your scope of work or building drawings to our engineering team for a free quote within 24 hours.