SPN engineering team using a Rebar Scanner to locate reinforcement in the concrete floor of a building under inspection
Non-destructive scanning for rebar location and concrete cover is a basic step when inspecting an existing building with no surviving construction drawings

What is Technical Due Diligence?

Technical Due Diligence (TDD) is an assessment of a building's technical condition to support a decision to buy, lease or invest. The goal is to reduce uncertainty before any money leaves your pocket. Unlike a general home inspection, which focuses on architectural finishes and building services, TDD goes deep into the structure's load-carrying capacity and the risk of future repairs.

← Scroll to see the full table →

IssueHome inspection / general handover checkTechnical Due Diligence
PurposeFind defects in finishes and building servicesAssess structural risk and repair budget before deciding
ScopeFinishes, paint, leaks, doors and windows, electrical, plumbingColumns, beams, slabs, foundations, piles, concrete strength, settlement
EquipmentVisual inspection and basic toolsNDT equipment per ASTM standards and actual load testing
ResultPunch list of finishing defectsReport certified by a licensed civil engineer (COE), with signature, license number and usage limitations
Usable in price negotiationTo a limited extentYes, because it is backed by numerical evidence

Why inspect before signing the contract?

Because risks you cannot see with the naked eye become the buyer's or tenant's burden the moment the contract is signed. The 5 most common risks are:

  • The building was designed for a different purpose — a warehouse designed for light storage, but the new tenant plans tall multi-level racking or heavy forklifts
  • No construction drawings or original test records — rebar sizes, pile depths and the design concrete strength are unknown
  • Past additions or alterations without engineer certification — added mezzanines, cored slabs, beams cut for pipe runs, or extensions built without calculations
  • Differential settlement — common in the soft clay areas of Bangkok and its vicinity, especially where an extension sits on a different foundation system from the main building
  • Deteriorated concrete and corroded reinforcement — common in seaside buildings, factories handling chemicals, and buildings with years of water leakage
📌 Key principle

The cost of an inspection is a one-time expense before you decide, whereas the cost of structural strengthening discovered later can no longer be negotiated. Inspecting first keeps all three options open: buy, negotiate, or walk away.

How many steps does the inspection involve?

A complete Technical Due Diligence usually has 5 steps: document collection, site survey, non-destructive testing, proof of actual strength, and the engineer's report. The results of each step define the scope of the next — it is not a matter of testing everything at once from day one.

The 5-step sequence of a pre-purchase or pre-lease structural inspection (Technical Due Diligence): the inspected area narrows while the depth of the answers increases Five cards arranged from left to right. Step one, document collection, such as as-built drawings, structural calculations and previous test results. Step two, visual site survey, recording cracks with a location plan. Step three, non-destructive testing: Rebound Hammer per ASTM C805, UPV per ASTM C597, rebar scanning and Half-Cell per ASTM C876. Step four, proof of actual strength with Core Test per ASTM C42 and C39, Floor Load Test per ACI 318-19 Chapter 27, and Parallel Seismic per ASTM D8381 for existing pile length. Step five, a report signed by a licensed engineer, summarizing usage limitations and remedial options. Below the cards are two bars: the first shows the inspected area starting from the whole building and narrowing to only the locations the previous steps flagged as risky; the second shows the depth of the answer and the cost per point rising in later steps. An arrow from step two notes that if steps one and two yield complete information and no warning signs, the scope of steps three and four becomes much smaller. The bottom bar shows the three options after receiving the report: buy or lease as planned, negotiate price or terms with numerical evidence, or walk away before signing. The actual scope is set by the responsible engineer. Technical Due Diligence: 5 steps, broad to deep Not to scale 1 Documents As-built dwgs Calculations Past test data 2 Site survey Visual check Crack log + location plan 3 NDT Rebound · UPV Rebar Scan Half-Cell ASTM C805 · C597 · C876 4 Strength proof Core Test Floor Load Test Parallel Seismic ASTM C42 · D8381 ACI 318-19 Ch. 27 5 Eng. report Use limitations Remedies Signed by PE NDT Core Area inspected: whole building Only spots flagged by prior steps Depth of answer / cost per point If steps 1–2 give full data and no warning signs → steps 3–4 shrink a lot (costly tests only where needed) ✓ Buy / lease as planned Fit for intended use ฿ Negotiate Price/terms with hard data ✕ Walk away Before signing
The 5-step sequence of a pre-purchase or pre-lease inspection: high-cost tests are used only at the locations that previous steps show to be genuinely at risk

What should be inspected? A 6-category checklist

A scope comprehensive enough to support a decision should answer questions in all 6 categories, from documents to settlement, as shown in the table.

← Scroll to see the full table →

CategoryQuestions that must be answeredCommon methods
1. Documents and drawingsAre as-built drawings, permits and structural calculations available? What alterations has the building undergone?Document review, owner interview
2. Visible structureAre there cracks that indicate structural problems? Are columns or beams deformed, or is concrete spalled with exposed rebar?Visual survey, photos and location plan
3. Concrete strength and reinforcementIs the concrete strength close to the design value? How is the rebar placed, is the cover adequate, and has it started to corrode?Rebound Hammer (ASTM C805), UPV (ASTM C597), Rebar Scan, Half-Cell (ASTM C876), Core Test (ASTM C42/C39)
4. Foundations and pilesWhat pile system was used, how long are the piles, are they damaged, and does the data match the drawings?Parallel Seismic (ASTM D8381), GPR (ASTM D6432), additional soil investigation where needed
5. Floor load capacityCan the floor really carry the new service loads, especially warehouse floors that will carry racking or machinery?Floor Load Test, Rebar Scan, review of structural calculations
6. SettlementIs the building settling differentially? Is settlement still ongoing or has it stopped?Level survey, installing monitoring points and tracking over time
📌 You do not always need to inspect every category

The right scope depends on the deal value, the building's age and the planned new use. A fairly new office building with complete drawings and no change of use may need only categories 1–3, whereas an old warehouse being converted into heavy-duty storage should be inspected in all 6 categories.

3D model of a cut-away warehouse showing where each of the 6 categories of pre-purchase or pre-lease inspection takes place, from documents to settlement (conceptual illustration) A conceptual 3D view of a warehouse with its front and right walls cut away, sitting on a block of soil that is cut open to show the foundations and piles under the front row of columns. Numbers 1 to 6 mark where each inspection category takes place. Number 1 is an engineer holding construction drawings in front of the building, representing documents and drawings. Number 2 is a diagonal crack on the rear wall and spalled concrete with exposed rebar on a column, representing visible structure. Number 3 is a concrete core hole and a technician scanning rebar on a column, representing concrete strength and reinforcement. Number 4 is the Parallel Seismic reference borehole casing installed parallel to a pile in the soil section, representing foundations and piles. Number 5 is storage racking transferring point loads to the floor through base plates, and a stack of test weights on the floor, representing floor load capacity. Number 6 is a level instrument on a tripod with a settlement monitoring point at a column base, representing settlement. A panel on the right summarizes each category with its common methods: as-built drawings, permits and calculations; survey of cracks and spalled concrete; Rebound Hammer, UPV, Rebar Scan and Core Test; Parallel Seismic and GPR; Floor Load Test; and level survey with monitoring points. The bottom bar summarizes that an office building with complete drawings and unchanged use may need only categories 1 to 3, an old warehouse being converted into heavy-duty storage should be inspected in all 6 categories, and if no documents exist at all the data must be rebuilt from the site. 3D model: where the 6 inspection categories sit in a building Not to scale 1 2 2 3 3 4 5 5 6 6 6-category checklist 1 Documents & drawings As-built · permits · calcs 2 Visible structure Cracks · spalling · deformation 3 Concrete & rebar Rebound · UPV · Rebar Scan · Core 4 Foundations & piles Parallel Seismic · GPR 5 Floor capacity Point loads · Floor Load Test 6 Settlement Level survey · monitoring pts A Office, full dwgs, same use May need only cat. 1–3 B Old warehouse → heavy storage Inspect all 6 categories C No documents at all Rebuild data from the site Conceptual · building shape and test points are examples Actual test layout set by the engineer for the planned new use
Conceptual 3D view — locations of the 6 inspection categories on a cut-away warehouse showing the foundations and piles. The numbers in the image match the categories in the table. The building shape and test-point locations are examples only.
A technician lowering a probe into a reference borehole beside a building foundation for a Parallel Seismic test to determine the pile length of a completed building
Category 4, foundations and piles, is the hardest information to obtain when no construction drawings survive. A Parallel Seismic test through a reference borehole beside the foundation helps estimate existing pile length without dismantling the structure.

Which test methods are used, and which standards apply?

Most test methods in this work are non-destructive (Non-Destructive Testing), so they can be carried out while the building is in use without disturbing existing tenants. Methods that take samples or apply real loads are used only where necessary.

← Scroll to see the full table →

MethodStandardWhat it answersImpact on structure
Rebound HammerASTM C805Assess concrete surface hardness and compare uniformity between membersNon-destructive
Ultrasonic Pulse Velocity (UPV)ASTM C597Check internal uniformity of the concrete and locate voids or internal cracksNon-destructive
Rebar Scanner / Cover MeterBS 1881-204Locate rebar and determine spacing and concrete coverNon-destructive
Half-Cell PotentialASTM C876Assess the probability of active rebar corrosionNon-destructive
Carbonation TestEN 14630 / RILEM CPC-18Measure the depth at which concrete has lost the alkalinity that protects the rebarMinor surface drilling
Ground Penetrating Radar (GPR)ASTM D6432Detect embedded objects under slabs and underground, slab thickness, pipe locationsNon-destructive
Parallel SeismicASTM D8381Estimate pile length under a completed buildingRequires a reference borehole
Core TestASTM C42/C39Measure actual concrete compressive strength from cored samplesLocalized destructive
Floor Load TestACI 318-19 Chapter 27Prove that the floor can carry the specified load without damageReal load applied
Pull-Out Test (chemical anchors)ASTM E488Check the holding capacity of bolts and anchors installed in the existing structureLocalized testing

For more on choosing a method, see NDT: non-destructive testing of concrete structures and NDT vs Core Test: what's the difference?

SPN engineering team on scaffolding performing an Ultrasonic Pulse Velocity test on a concrete beam above the ceiling inside a building that remains in use
Non-destructive testing can be done while the building stays open; it only needs scaffolding to reach the test points and local ceiling openings, so existing tenants are not disturbed during the pre-decision inspection

Which documents should you request from the owner before the inspection?

Request 8 documents, starting with the as-built drawings and structural calculations. The more complete the documents, the smaller and cheaper the on-site testing scope becomes.

  • As-built drawings, especially the structural and foundation drawings
  • Structural calculations and the design live load for each floor
  • Building permit and alteration permit (if there have been additions)
  • Soil investigation report from the original project
  • Previous pile test results, such as Seismic Integrity Test or Dynamic Load Test reports
  • Concrete compressive strength test results from construction
  • History of repairs, strengthening, and any flood or fire events
  • Annual building inspection reports under the Building Control Act (for buildings that fall under it)
⚠️ If the owner has no documents at all

This is common with warehouses and old buildings. Treat the structural information as zero and rebuild it entirely through on-site testing, which makes the scope and budget higher than usual. Allow for this time and budget from the negotiation stage.

Which warning signs mean you should stop and investigate further? (7 signs)

The following 7 signs do not mean the building is unusable, but they do mean you need more information before deciding.

  • Diagonal cracks at column heads or beam ends — unlike map cracking in plaster, these are directly related to forces in the structure
  • Floors or doors clearly out of level — possibly caused by differential settlement
  • Concrete spalled enough to expose corroded rebar — the steel cross-section is reduced, and so is the load capacity
  • Gaps between the main building and an extension — indicating the two parts are settling unequally
  • Slabs cored or beams cut to route building services — especially without engineer certification
  • Mezzanines or storage levels added later — can easily exceed the original design load
  • The owner refuses access to certain areas — a management red flag that deserves as much caution as the technical ones

If the building is old or has been altered several times, see Structural assessment of old buildings before renovation, and if the main concern is the foundations, see Pile inspection before buying a building

Concrete core sampling (Core Test) from a building structure for compressive strength testing in the laboratory
When non-destructive results suggest the concrete strength may be below design, a localized Core Test is the method that gives the actual compressive strength to use in calculations

What extra checks do warehouses and factories need?

Warehouses and factories need special attention to floor load capacity, because service loads are high and concentrated at points. Compared with office buildings, there are 5 additional items to check:

  • How much the floor can really carry — racking transfers load to the floor as point loads through base plates, not as a uniformly distributed load, so the figure in marketing documents is usually not enough to base a decision on
  • Slab on ground or pile-supported slab — a slab on ground in soft-soil areas is likely to settle over time, unlike a slab that transfers load directly to piles
  • Forklift and truck routes — wheel loads and repeated impact damage the floor faster than in static storage areas
  • Floor flatness — critical for high-bay racking or narrow-aisle forklifts
  • Steel roof structure and connections — especially if building services, fire-protection piping or crane rails will be hung from it

For more on floors and how to prove their capacity, see How much load can a factory or warehouse floor carry, and how to prove it

Dial gauges installed under a building floor slab to measure deflection during a Floor Load Test with real loads
When no documents confirm the floor's design load, a Floor Load Test proves it with real loads, measuring deflection under the slab and assessing it against the ACI 318-19 Chapter 27 criteria

How long does the inspection take?

Typically, site work takes 1–2 days per building and the final report about 7–14 working days, depending on the scope. Build this time frame into your negotiation schedule from the start.

1–2 days
Site work for a standard inspection package per building
2–3 days
Per Floor Load Test point
7–14 working days
Final report signed by the engineer

If the deal has a tight signing deadline, start with steps 1–3 to get an overview of the risks, then write contract conditions that cover the step 4 test results that will follow later.

How much does it cost?

Cost depends on the methods used, the number of test points, access difficulty and site distance; it is not a lump-sum price per square meter of building. The table below compares relative price levels to give you a picture before requesting a quote.

← Scroll to see the full table →

PackageBest forIncludesPrice level
Initial screeningBuilding with complete drawings, continuing the same useVisual survey + Rebound Hammer + Rebar Scan💰
Pre-purchase or pre-leaseGeneral buildings needing enough data to make a decisionScreening package + UPV + Half-Cell + level survey💰💰
Strength proofChange of use, added loads, or warning signs foundPre-purchase package + Core Test + Floor Load Test + Parallel Seismic as needed💰💰💰

The 💰 levels above are only a relative comparison between packages, not a service price list. For a detailed pricing breakdown see Structural inspection NDT prices 2026, or send us your scope to get a free quotation within 24 hours.

Price note: This price excludes travel and equipment mobilization costs, which are charged extra depending on the distance to site.

How can you use the results in negotiations?

Use them as numerical evidence to adjust the price, set conditions, or limit use in the contract. A report certified by an engineer carries weight in negotiations because it turns subjective concerns into numbers that can be discussed. There are 4 practical approaches:

  • Adjust the price by the estimated repair budget — use the estimated strengthening or repair cost as the basis for negotiation
  • Require the seller to carry out repairs before transfer — define the repair scope and acceptance criteria clearly in the contract
  • Write usage limitations into the lease — such as the maximum floor load for each zone, to prevent later disputes
  • Hold back part of the payment (retention) — until the remaining test results are complete

Summary

A pre-purchase or pre-lease structural inspection is not about finding fault with the building, but about knowing what you are paying for and how far the building can support your planned use. There are 3 key points:

  • Consider all 6 categories, then choose the scope based on building age, deal value and the new use
  • Obtain as many existing documents as possible to reduce on-site testing scope
  • Have the responsible engineer set the test layout for the intended new use, rather than following an off-the-shelf checklist