How Do Solar Farm Foundations Differ from Building Foundations?

The difference is the load that governs design. Building foundations mainly carry compression, while solar farm piles mainly resist wind uplift and lateral push. In a building, the weight of the structure, floors, walls and live loads presses down at all times, so the piles are pushed into the ground and uplift plays almost no role.

Solar farm foundations are the reverse. The mounting structure is a very lightweight steel frame, but the solar panels are wide, flat surfaces tilted toward the sun. When wind blows under the panels, it creates uplift and lateral forces that transfer directly to the piles. The small self-weight of the structure is not enough to counteract the uplift.

As a result, solar farm piles are usually governed by uplift and lateral loads, not compression. A pile that carries compression comfortably can still be pulled out under the design wind gust. Solar farm pile testing therefore uses a different set of tests from ordinary buildings.

SPN engineer holding a clipboard with pile test data on a solar farm project site, showing pile number, pile type and design load
Pile testing on a solar power plant project: the pile number, pile type and design load are recorded on site before every test (Photo: SPN Soil Engineering)

Which Pile Tests Does a Solar Farm Need?

There are 3 core items: soil investigation, uplift testing and lateral load testing. Each answers a different question and is done at a different stage of the project, as shown in Table 1.

← Scroll to see the full table →

Table 1 — Core tests for a solar farm project
ItemWhat it answersWhenReference standards
Soil investigation
(Soil Boring + SPT)
What are the soil layers across the site, where are the soft clay or loose sand zones, and what is the groundwater level?Before foundation designASTM D1586 (SPT)
Uplift test
(Uplift / Tension Test)
Does the pile resist the design uplift, and at what load does it start to move upward?After installing test piles, before proceeding with production piles across the siteASTM D3689/D3689M-25
Lateral load test
(Lateral Load Test)
How far does the pile move laterally at the design load, and is that within the limit the mounting structure can accept?Together with or after the uplift testASTM D3966/D3966M-22

Some projects also add a compression test to ASTM D1143/D1143M-20e1, especially when concrete piles are used in soft soil areas or there are heavy structures such as inverter buildings and transformers. The principle of this test is explained in What Is a Static Load Test. For projects using driven steel piles or ground screws, the tests that decide the design are usually uplift and lateral load. Read the details of each test method in Pile Uplift Test (Tension Test) and Lateral Load Test for Piles.

The diagram below summarizes everything in one figure. The left panel shows the three forces at the head of a solar panel pile and the soil resistance against them. The right panel matches each force with its test method, standard and what is measured. The bottom strip lists the project's test sequence in time order, from soil investigation to random testing of working piles.

A solar panel pile carries three forces: wind uplift, lateral push and a small compression from self-weight. Each is matched with its test method, ASTM standard and what is measured, together with the test sequence for the whole project. A diagram with two panels and a bottom strip. The left panel is a side view of a tilted solar table on a single steel pile. Wind blows under the panels and pushes them up. At the pile head there are three arrows: an orange upward arrow for uplift, which governs design; a blue arrow pointing right for lateral force; and a small navy downward arrow for the small compression from the weight of the panels and steel frame. In the soil, green downward arrows along the pile shaft represent skin friction resisting pullout, which is limited because the pile is short with little contact surface. A horizontal green arrow on the upper right represents the upper soil resisting lateral load, and a note at the pile toe says end bearing helps only in compression and does not resist pullout. Below the figure are the three pile systems found on solar farms with points to watch during testing: driven steel piles with H, C or W sections need a head-gripping detail designed so the steel does not twist or tear; Ground Screw piles need installation torque recorded; and concrete piles need sufficient embedment length of the reinforcement at the pile head. The right panel matches forces with tests in three boxes. Box one: uplift, tested by Uplift or Tension Test to ASTM D3689/D3689M-25, measuring pile-head rise at each tension load step, used to decide whether the pile resists the design uplift and at what load it starts to move up. Box two: lateral load, tested by Lateral Load Test to ASTM D3966/D3966M-22, measuring lateral movement of the pile head, used to decide whether it is within the limit the mounting structure can accept. Box three: compression, only on some projects, tested to ASTM D1143/D1143M-20e1, measuring settlement at each load step, used for concrete piles in soft soil or foundations for heavy structures such as inverter buildings and transformers. Below the boxes a note says uplift capacity is not obtained by multiplying compression capacity by a ready-made factor; it must come from actual testing, and design loads and acceptance criteria are set by the design engineer. The bottom strip lists the project test sequence in four steps: soil investigation before design and zoning; install test piles then run uplift and lateral load tests; the designer reviews results before ordering piles for the whole project; and install production piles then randomly test working piles at the proportion set by the specification. Loads on solar farm piles → which tests? Not to scale 1 Loads on a solar panel pile Light frame + wide panels → uplift & lateral govern Tilted solar panel Wind below 3 Panel + frame wt. Small → low compr. 1 Uplift Often governs 2 Lateral (Lateral) Skin friction Resists uplift Short pile = limited Upper soil Resists lateral Toe: compression only Common pile systems · test cautions Driven H/C/W Design head grip No twist/tearing Ground Screw Record torque at installation Concrete pile Rebar embedment at head adequate 2 Each load → which test? Load vs. test method, standard, measurement 1 Wind uplift Test Uplift / Tension Test Standard ASTM D3689/D3689M-25 Measures Head rise per tension step Decide Meets design uplift? · Load at onset of rise 2 Lateral push Test Lateral Load Test Standard ASTM D3966/D3966M-22 Measures Lateral head movement vs. load Decide Within mounting structure limit? 3 Compression · some projects Test Compression Load Test Standard ASTM D1143/D1143M-20e1 Measures Head settlement per load step Use when Concrete pile in soft soil · inverter/transformer Uplift ≠ compression × fixed factor Toe gives no uplift resistance; values must be tested Design load & criteria: set by designer Project test sequence (in time order) 1 Soil investigation SPT · ASTM D1586 Before design · zoning 2 Test pile Uplift + lateral tests (+ compr. if specified) 3 Review → order Designer confirms pile type & length 4 Install piles Random working pile tests at spec proportion
Left: wind blowing under the panels creates uplift (1) and lateral force (2) at the pile head, while compression from the weight of the panels and frame (3) is small. The soil resists pullout only through skin friction, because the pile toe helps only in compression. Right: uplift is tested by Uplift Test to ASTM D3689/D3689M-25, lateral force by Lateral Load Test to ASTM D3966/D3966M-22, and compression only on some projects to ASTM D1143/D1143M-20e1 — conceptual diagram, not to scale; design loads and acceptance criteria follow the project specification.

Why Does Uplift Govern Solar Farm Pile Design?

Uplift governs design because fewer mechanisms resist uplift than resist compression. When a pile is pushed down, load transfers to the soil in two ways: skin friction along the pile shaft and end bearing at the pile toe. When a pile is pulled up, end bearing disappears entirely, leaving only skin friction plus the pile's own weight.

In addition, skin friction in tension is often lower than in compression, because pulling reduces the stress in the soil around the pile. The same pile therefore usually carries clearly less uplift than compression. Usable values must come from on-site testing, not from taking the compression capacity and multiplying it by a ready-made factor.

💡 An often overlooked point

Most solar farm piles are short with little contact surface, so the skin friction resisting uplift is limited. Adding just a little pile length can often change test results significantly, which is why testing should be done before ordering piles for the whole project.

How Is Testing Different for Steel Piles, Ground Screws and Concrete Piles?

Solar farms in Thailand use 3 main pile systems: driven steel piles, ground screws and concrete piles. Each system has different points to watch during testing.

1. Driven Steel Pile

These are H, C or W structural steel sections driven straight into the ground. They install quickly and can be removed. The point to watch is corrosion in saline or highly acidic soil, which affects the project's service life of 25 years or more. For uplift testing, the pile-head gripping detail must be designed so the steel does not twist or tear before the soil fails.

2. Ground Screw / Helical Pile

This is a steel shaft with helical plates screwed into the ground. The helices increase uplift resistance compared with a straight pile of the same size, making them suitable where high uplift capacity is needed without going very deep. Testing must also record the installation torque, because it is an indicator of installation quality that can be compared across the whole site.

3. Concrete Pile

Used when soft soil requires deeper piles or when steel corrosion is a concern. Its self-weight helps resist uplift, but the weak points are splices and the reinforcement embedment at the pile head, because uplift pulls directly on the reinforcement. If the development length is insufficient, failure occurs at the pile head before the soil fails, and the soil capacity cannot be read.

Steel reaction frame for a static compression load test on piles, set on concrete block cribs on both sides at the project site
Reaction system for a static load test: the load from the jack is transferred up to the reaction beam and then down to supports placed far enough from the test pile not to disturb the soil around it (Photo: SPN Soil Engineering)

Which Soils Pose a Risk to Solar Farm Piles?

There are 3 soil groups to watch: saline soil that corrodes steel, loose sand, and flood-prone areas or expansive soil. Solar farms are usually built on land outside towns, which often has soil conditions unsuitable for ordinary construction, so all three groups must be checked clearly from the soil investigation stage.

Saline and steel-corrosive soils Areas near the coast, former salt fields, or areas with saline groundwater greatly accelerate corrosion of steel piles. The soil investigation should collect samples to test soil resistivity, pH, and chloride and sulfate content, so the designer can choose between thicker galvanizing, a corrosion allowance in thickness, or switching to concrete piles. Read how it is measured in Soil Resistivity Test for Solar Farms.

Loose sand provides low skin friction and is sensitive to vibration. Uplift capacity measured in loose sand is often lower than expected from SPT values alone, so actual test results matter more than formula estimates. Read how to interpret SPT values in How to Interpret SPT N-Values.

Flood-prone areas and expansive soil Where the groundwater level rises and falls with the seasons, soil strength changes back and forth, so values measured in the dry season may not apply in the rainy season. Clays that swell and shrink with moisture can push or pull short piles. The report should always state the groundwater level encountered and the testing period. The installation level of panels and equipment in flood-risk areas is set from the flood study results (Flood Study).

If the project is still at the land selection stage, checking soil conditions before deciding to buy greatly reduces risk. Read the items to check in Before Buying Factory Land: An Engineer's Soil Checklist, which applies the same principles to solar farm land.

How Should Pile Test Locations Be Planned Across a Solar Farm Site?

The principle is to divide the site into zones based on soil investigation results and then spread test locations to cover every zone, rather than using results from one location to represent the whole site. Solar farms cover very large areas, some projects several hundred rai, and the soil layers can differ completely from one corner to another. Using results from a single borehole or a single test pile for the whole site is therefore a risk not worth taking.

The common approach is to divide the area into zones by topography and soil investigation results, then spread test locations to cover every zone, especially zones where boring results differ from the rest. The appropriate number of boreholes and test piles depends on site size, soil variability, and the requirements of the designer or project owner. Read the principles for setting the number of boreholes in How Many Boreholes and How Deep.

Test locations should also be separated by pile system, because different pile types and lengths give very different results. If a project uses more than one pile system or several lengths, the test results of one type cannot represent another. For projects using ground screws, the recorded installation torque helps compare installation quality across the whole site.

The sequence that makes test results most useful is: soil investigation before design → install test piles and complete uplift and lateral load tests before ordering piles for the whole project → proceed with production pile installation → randomly test working piles at the proportion set by the specification. Projects that test after all materials have been ordered have far fewer options if the results are not as expected. The difference between these two stages is explained in Test Piles vs. Working Piles: What Is the Difference.

The 3D view below models one block of a solar farm divided into 3 soil zones. Note that every zone has its own boreholes and its own uplift and lateral test locations, while compression test locations are only at some points. The box on the right summarizes 5 principles for placing test locations; the actual number of locations must be set for each project.

3D model of a solar farm site layout divided into three soil zones, showing soil investigation boreholes and pile uplift, lateral and compression test locations in each zone, together with principles for planning test locations across the site. A conceptual 3D view, not to scale, of one solar farm block. The ground surface has six rows of tilted solar tables. A grey internal road runs lengthwise through the middle of the site. Dashed lines divide the site into three soil zones: Zone A, soft clay with a deep soft layer where concrete piles may be used; Zone B, loose sand, where measured uplift capacity is often lower than expected from SPT values; and Zone C, low-lying land with saline soil, shallow groundwater and fast steel corrosion. The soil sections on the front and right faces of the soil block show different layers in each zone, and Zone C has a blue dashed line showing the shallow groundwater level. The front edge of every zone has a soil boring rig and borehole line with SPT sampling points on the section. Marker pins show pile test locations: orange circles are uplift test locations and blue squares are lateral test locations; every zone has both, and Zone C has one additional uplift test location. Navy triangles are compression test locations, done only at some points: in the soft soil zone using concrete piles and at the inverter and transformer buildings, which are heavy structures. A legend for the zones and symbols is below the figure. The box on the right summarizes five planning principles: divide zones by topography and soil investigation results before placing locations; every zone must have uplift and lateral test locations, with emphasis on zones whose soil differs from the rest; separate test locations by pile system because different types and lengths give different results, and ground screws can use installation torque for comparison across the site; in saline zones measure soil resistivity, pH, chloride and sulfate; and in shallow groundwater zones record the groundwater level encountered and the testing period. Below the box it states that there is no fixed number of test locations; it depends on site size, soil variability and project specification, and is set jointly by the designer, project owner and testing firm. This is a conceptual image; the number and positions of locations are not to actual proportion. 3D model: test locations across a solar farm Not to scale A B C Boreholes + SPT, all zones Soil profile differs by zone Inverter / transformer bldg. Heavy → may need compr. test Shallow GWL (Zone C) Record GWL + test period Uplift · ASTM D3689 Lateral · ASTM D3966 Compr. (some) · ASTM D1143 Soil borehole + SPT Soil zones from boring (example) A Soft clay Deep soft layer → concrete pile? B Loose sand Uplift often below SPT estimate C Low-lying · saline Shallow GWL · fast corrosion Conceptual · counts & positions not to scale · dashed lines = zone limits Site-wide test layout rules 1 Zone before placing by topography + boring results 2 Test points in all zones Uplift + lateral Focus on atypical zones 3 Split by pile system Type/length differ → results differ Ground Screw: compare torque 4 Saline zone Resistivity · pH Chloride · sulfate (soil + water) 5 Shallow GWL zone Record GWL found + test period in report No. of points: not fixed Depends on site size, variability of soil layers, and project spec Set jointly by Designer · Owner · Tester
3D model of a solar farm site divided into 3 soil zones based on soil investigation results: every zone has its own boreholes + SPT and its own uplift (●) and lateral (■) test locations. Compression test locations (▲) are only in the soft soil zone where concrete piles may be used and at the inverter/transformer buildings, while the low-lying zone has shallow groundwater whose level must be recorded in the report — conceptual image; the number and positions of locations are not to actual proportion. The actual number of test locations is set jointly by the designer, project owner and testing firm.
Reaction beam on supports on both sides, with a jack and displacement gauges at the pile head, for a pile uplift test
Uplift testing on site: the jack pulls the pile head up while transferring load to supports on both sides; the uplift gauges are mounted on a reference beam independent of the loading system (Photo: SPN Soil Engineering)

How Much Does Solar Farm Pile Testing Cost, and How Much Time Should You Allow?

Solar farm pile testing is priced per project based on the actual scope, because it depends on site size, number of soil zones, number of test locations and maximum test load. For reference, SPN's soil investigation for general projects starts at about THB 20,000-40,000 (2-3 boreholes, including basic laboratory testing and a report certified by a civil engineer licensed by the Council of Engineers Thailand (COE)). For solar farm projects requiring many boreholes, plus uplift and lateral load testing, please contact us for a free quotation within 24 hours.

Note: This price excludes travel and equipment mobilization costs, which are charged according to the distance to the site. Most solar farm projects are in the provinces, so state the site location when requesting a quote to get a realistic figure.

For scheduling, plan soil investigation and test pile testing ahead of the pile ordering date, because you need to wait for the results and for the designer to review them. The actual duration depends on the number of zones and test locations, so it is stated in each project's quotation. SPN provides pile testing for uplift, lateral and compression loads nationwide across all 77 provinces.

⚠️ This article provides general information

This content explains the principles for selecting tests for solar farm projects for general understanding only. Design uplift and lateral loads, pile length and size, number of test locations, and acceptance criteria must be set by the project's design engineer based on actual test results.