How Does the 2023 Ministerial Regulation Govern Spread Footing Design?
A spread footing (shallow foundation) transfers the building load directly into the ground without piles. It is commonly used where the ground is stiff, such as in Eastern Thailand, the Northeast (Isan) or foothill areas. The Ministerial Regulation on Building Foundations and Ground Supporting Buildings B.E. 2566 (2023) (for an overview of the whole regulation, see The 2023 Foundation Ministerial Regulation Simply Explained) sets the principle that the allowable bearing pressure must not exceed one third of the ultimate bearing capacity of the foundation soil — equivalent to a factor of safety FS = 3.
Soil bearing capacity is obtained in two main ways: by calculation from the engineering properties of the soil found in the soil investigation, or by evaluation from field test results (for the basics, see What Is Soil Bearing Capacity?).
What Does the 200 kPa Threshold Mean in Practice?
The game-changer for spread footing designers is this condition: when the designer wants to use an allowable bearing pressure above 200 kPa (approx. 20 t/m²), the Ministerial Regulation requires the value to be confirmed by an in-situ plate bearing test (Plate Bearing Test) on the actual site. Calculation from boring results alone is not enough — what was once just good practice is now a legal condition.
In practical terms:
- Projects on stiff ground that want smaller footings (using high bearing values) — book the plate bearing test into the schedule from the design stage.
- Factories, warehouses and heavy machine foundations — high footing loads make these the most likely to hit this condition (see also the soil checklist before buying factory land).
- If the value used is 200 kPa or less — design from soil investigation results and normal calculation; testing is not mandatory.
If a project has neither soil investigation results nor field test results, the Ministerial Regulation limits the design to presumptive bearing values, which are low and make footings much larger. Read more in No soil boring: what bearing values does the law allow?
The figure below sums up the 200 kPa dividing line in a single bar, together with a conceptual section explaining why a passed plate bearing test still cannot replace a soil investigation.
What Is a Plate Bearing Test? (Short Version)
In short, a plate bearing test places a standard steel plate on the soil at foundation level and loads it in increments with a hydraulic jack, measuring the plate settlement at each increment. The result is the load–settlement curve of the actual soil at the footing location. The test follows DPT standard 1253-62 and ASTM D1195 / D1196, together with the criteria set by the design engineer. This article does not go into the equipment and procedure, because we already have a full guide at Plate Bearing Test: Testing the Load-Bearing Capacity of Soil.
Who Is Responsible, and When Should It Be Planned?
- Design engineer — decides the bearing pressure used in the design, and therefore whether the project falls under the testing requirement, as well as the number of test points, their locations and the maximum test load.
- Project owner — responsible for procuring the test and allowing time in the schedule, because the test must be performed at actual foundation level and is usually tied to when excavation opens up.
- Testing provider — must deliver a test report signed and certified by an engineer, so the designer can use it in the calculations and the building permit application (see what a complete report contains in the legally compliant soil investigation report checklist).
A common mistake is realizing the test is needed only after the design is finished or the site has already been excavated, which halts work while waiting for results. The better approach is for the designer to specify the testing requirement from the preliminary design stage and locate the test points together with the soil boring plan.
The sequence that keeps the site from stopping to wait for results is to mark the test points in the plan from the design stage, then open the test pits to foundation level following the same plan as the boreholes, as shown below.
Plate Bearing Test vs. Soil Investigation: Can One Replace the Other?
← Scroll to see the full table →
| Issue | Soil investigation (Soil Boring) | Plate Bearing Test |
|---|---|---|
| What you get | Soil layers over full depth, SPT, samples for laboratory testing | Actual load-bearing behavior of the soil at foundation level |
| Depth reflected | Full borehole depth | Only the shallow zone under the plate (about 2× the plate size) |
| Used for | Designing all foundation types; choosing the foundation type | Confirming high bearing pressures for spread footings |
| Legal status | Mandatory for building categories specified in the Ministerial Regulation | Mandatory when using values above 200 kPa |
In short, they are not interchangeable but complementary — soil investigation tells you the whole soil profile for design, while the plate bearing test proves the value you actually want to use when the legal condition applies. Projects that fall under the rule therefore usually need both (for which building categories require a soil investigation, see the Ministerial Regulation summary).
Why Is a Soil Investigation Still Needed After a Passed Plate Bearing Test?
The test plate is only 0.3–0.75 m across, so the load spreads into the soil as a stress bulb only about twice the plate size deep. An actual footing is many times wider than the plate, so its stress bulb reaches much deeper. If a soft layer lies deeper than the plate can "see", the test result will look good, yet the actual footing can still settle due to that soft layer (see the section in the 200 kPa threshold section). Soil layer data over the full depth from boreholes is therefore something the designer must always check alongside.
Summary
The 2023 Foundation Ministerial Regulation upgrades the plate bearing test from an "option" to a "requirement" for spread footings designed with an allowable bearing pressure above 200 kPa under the FS = 3 principle. Anyone designing factories, warehouses or buildings on stiff ground who wants to get the most out of their footings should put this test in the schedule from the outset and plan it together with the soil investigation, to get complete data on both counts. See the full scope of plate bearing test and soil investigation services at Soil Investigation and Testing Services.
This article summarizes the Ministerial Regulation for general understanding only. It is not legal or engineering advice for any specific project. For practical use, refer to the official text of the Ministerial Regulation as published in the Royal Gazette and consult the licensed engineer for your project.