Most of SPN's instrumentation work is on the soft-clay plains of central Thailand, but inclinometers are equally suited to slopes and embankments and are the main tool for finding the plane on which a slope is moving. This case study draws on the inclinometer casing installation at the Kraseaw Hydropower project in Dan Chang District, Suphan Buri. The site is in the foothills, so the ground is completely different from Bangkok. For the basic principles of the instrument, see What is an inclinometer?, which has a section dedicated to slopes.

What Was the Brief for This Job?

The brief was to find out whether the slope at the construction site was moving, at what depth, and how the rate of movement changed in the rainy season. The project involves construction on ground with slopes and cut-and-grade earthworks in the foothills. SPN was responsible for drilling borehole BH-1, installing the inclinometer casing and taking the baseline readings. The same borehole was used to log the soil layers during drilling.

Unlike Bangkok, the ground here is colluvium (hillslope sediment) over weathered rock and bedrock, and layer thicknesses change rapidly over short distances. The casing depth therefore cannot be fixed from the drawings; it has to be decided from the soil and rock actually recovered from the hole. For the principles of slope stability and why slopes move, see Slope stability and F.S. and What causes landslides and how to prevent them.

SPN drill rig installing inclinometer casing in BH-1 at a foothill site, Kraseaw Hydropower project, Dan Chang District, Suphan Buri, with project signboard
Drilling and installing inclinometer casing in BH-1, Kraseaw Hydropower project, Dan Chang, Suphan Buri — a foothill site where drilling had to pass through colluvium into a layer considered stable (Photo: SPN Soil Engineering)

How does installation in hillside ground differ from soft clay?

Installing an inclinometer in hillside ground differs from soft clay in that the "non-moving layer" is dense weathered rock or bedrock, and its level must be confirmed by actual drilling. The principle is the same as any job: the casing tip must be embedded in a layer that does not move. On a slope, this means the layer below every possible slip surface, so the casing must be drilled deep enough into it, not just touching it. If the actual slip surface is deeper than the casing tip, the whole profile shifts and you cannot tell where the ground is moving.

There are three steps that differ from soft-clay work. The measurement method follows ASTM D6230, as for deep excavations.

  • Drilling: change the drilling method when passing from soil into weathered rock, and record the level of each layer change in detail (see the guidance in Rock coring).
  • Groove alignment: orient the A-axis downslope, in the expected direction of movement, not perpendicular to a wall line as in a deep excavation.
  • Backfilling: in fractured weathered rock, watch for grout loss, because it leaves the casing poorly coupled to the ground and the readings will not reflect actual movement.

The 3D view below is a conceptual illustration of the BH-1 location on a foothill slope. It shows the casing passing through the colluvium and the possible slip surface, with the tip embedded in rock. The part of the casing above the slip surface is displaced downslope as the soil mass moves, creating a kink at the shear zone. This is not a project drawing or actual monitoring data.

Conceptual 3D model of inclinometer BH-1 on a foothill slope; the casing passes through the possible slip surface and is embedded in a stable layer Conceptual 3D view of a foothill slope cut away to show a cross-section; not a project drawing or actual monitoring data. The ground surface steps down from high ground on the left to a mid-slope bench and the flat toe on the right. The section has three layers: colluvium on top, weathered rock in the middle and bedrock at the bottom, each of uneven thickness. The red dashed line is the possible slip surface within the colluvium near its contact with the weathered rock; the soil mass above it is shaded light red. On the bench are a drill rig and inclinometer BH-1 (purple line), drilled through the slip surface with its tip embedded in dense weathered rock down to bedrock. The casing above the slip surface is offset downslope relative to a dashed line showing the original casing alignment, forming a kink at the shear zone (exaggerated). The orange arrow on the bench shows the A-axis groove direction pointing downslope; the blue arrows show rainwater infiltrating in the rainy season. The right panel summarizes how to read the figure: the casing tip must be in a stable layer, the A-axis groove points downslope, the kink in the profile marks the shear zone, and readings should be more frequent in the rainy season. 3D model: Inclinometer BH-1 on a foothill slope Not to scale Colluvium Weathered rock Bedrock 1 Rain infiltration Rainy-season trigger 2 Inclinometer BH-1 Guide pipe + rig 3 A-axis downslope Expected movement 4 Possible slip surface Casing "kinks" here (exagg.) 5 Tip in stable layer Dense weathered rock/bedrock How to read this Tip must be in stable layer Below all possible slip surfaces A-axis groove downslope In expected movement direction Rainy season: read more often Infiltration = trigger Kink = shear zone level Cumulative displacement → Mass moves as a block Shear zone Below zone Near zero z Line holes up/downslope With piezometers (general) Conceptual, not measured data
3D model (conceptual) — ① Rainwater infiltrates the ground, accelerating movement in the rainy season ② Inclinometer BH-1 casing and drill rig on the slope ③ A-axis groove points downslope in the expected direction of movement ④ Possible slip surface — the casing "kinks" at this level (exaggerated) ⑤ Casing tip embedded in a stable layer, i.e. dense weathered rock or bedrock. The right panel shows the profile shape kinking at the shear zone. Soil layers, depths and slip-surface shape are hypothetical, not project data (Image: SPN Soil Engineering)

How are readings taken, and how do they differ from deep excavations?

On slopes, readings are scheduled by time and season and monitoring often runs for a year or more, unlike deep excavations, where readings follow the excavation stages and end when the underground structure is complete. The baseline is read several times after installation, followed by routine readings, with frequency increased in the rainy season or after prolonged heavy rain, because infiltrating water directly accelerates slope movement. Where continuous data are needed, in-place inclinometer probes can be installed and connected to a datalogger with automatic alarms. See the comparison in Manual vs Automatic Monitoring.

← Scroll to see the full table →

TopicSlope (this case)Deep excavation in soft clay
Reading scheduleBy time and season, more often in the rainy seasonBy excavation and strut installation stages
Monitoring durationOften a year or more, through the rainy seasonEnds when the underground structure is complete
A-axis directionDownslopePerpendicular to the wall line
Plot shapeKinks at the shear zone; the soil mass above moves almost as a single blockBulges in the middle because the wall is restrained at top and bottom
Illustrative example plot of cumulative slope displacement versus depth from an inclinometer monitored over several months, showing the kink at the slip surface and the top-of-casing value by reading round The left plot shows cumulative downslope displacement from 0 to 40 mm on the horizontal axis and depth below the top of casing from 0 to 24 m on the vertical axis. Below 13 m every line is zero; above 11 m every line is nearly vertical, showing the soil mass moving as a block. Between 11 and 13 m the lines kink abruptly, marking the shear zone or slip surface. Top-of-casing values: 4 mm at month 2, 8 mm at month 4, 19 mm at the end of the rainy season and 21 mm in the following dry season. Upper right is a slope cross-section with the inclinometer casing passing through the moving soil mass and its tip embedded in the stable layer; the slip surface is at about 12 m, and stabilization measures must cut through this plane. Lower right is a plot of the top-of-casing value by reading round, rising quickly in the rainy season and slowing in the dry season; if the rate keeps accelerating within the same rainy season, that is a warning sign. The bottom strip lists the principles: find the kink to know the slip-surface level, track the rate of movement by season, and place at least two to three holes in a line up and down the slope together with piezometers. This is an illustrative example plot, not actual project monitoring data. Slope inclinometer: the plot “kinks” at the slip surface Conceptual graph · Not measured data 0 10 20 30 40 0 4 8 12 16 20 24 Cumulative downslope displ. (mm) ← Depth below casing top (m) Shear zone 11–13 m Baseline Month 2 · 4 mm Month 4 · 8 mm End of rains · 19 mm Next dry · 21 mm Moving mass as a block Slope section: casing crosses plane Slip surface Inclinometer casing Tip in stable layer Top-of-casing value by round 0 10 20 M0 M2 M4 End rain Dry Rainy ↗ mm 1 Find the kink = slip surface level 2 Rate by season Accel. in rains = warning 3 Holes in a line 2–3 holes + piezometer
Inclinometer results on slopes and embankments — unlike deep excavations, the plot does not "bulge" but "kinks" at a single level, which is the slope's slip surface. The near-vertical profile above the kink shows the soil mass moving as a block, and acceleration during the rainy season is the signal to watch. Lower right is the top-of-casing value by reading round (illustrative example plot showing the typical pattern for this type of work, not actual project monitoring data)

How are results interpreted, and what does the kink tell you?

The kink in the profile is the level of the shear zone or slip surface, and it is the first thing an engineer looks for on a slope. The telltale sign is a soil mass above a certain level moving almost uniformly as a block, with values dropping abruptly over a short depth range. Knowing this level changes every decision, because stabilization measures — drainage, regrading or earth-retaining structures — must be designed to cut through this plane to be effective.

The other thing to watch is the rate of movement, from the plot of maximum value versus time. Many slopes creep slowly each rainy season and stop in the dry season, which is acceptable to a degree. But if the rate keeps accelerating within the same rainy season without slowing, that is a warning sign of failure that must be reported immediately. Alarm levels for each project are set by the design engineer from a site-specific stability analysis; there is no universal figure.

What are the lessons from the Dan Chang project?

There are three lessons from Dan Chang: casing depth is decided on site, a single hole tells you about only one location, and mountain sites need access planned from the outset.

  • Casing depth is decided on site. The weathered rock level actually encountered determines the casing length, so the drilling team must bring spare casing and be empowered to decide on the spot together with the design engineer.
  • A single inclinometer tells you about only one point. On slopes where the shape of the slip surface across the whole slope is needed, place at least 2–3 holes in a line up and down the slope, ideally paired with piezometers to link movement to water levels (see What is a piezometer?). The number and locations are as specified by the design engineer.
  • Mountain sites are about access. Access routes to the hole in the rainy season, safety of the reading team, and protecting the casing top from runoff must be planned from the time the hole location is chosen.

For another type of slope and hillside-cut project that SPN designed and monitored, see Case study: retaining wall for a hillside cut slope. For inclinometers in a soft-clay deep excavation, where the plot pattern is completely different, compare Case Study: Inclinometer in a deep excavation, Bang Phli. If you are unsure whether your project needs instrumentation, see When is instrumentation required?

Fees for instrument installation and reading depend on the type and number of instruments, installation depth and reading frequency, so they are estimated per project. Contact us for a free quotation within 24 hours. Prices exclude travel and equipment mobilization costs, which are charged extra depending on the distance to site.

⚠️ Note on the case study data

Project details and photographs are from an actual SPN installation. All graphs in this article are conceptual examples showing result patterns typical of similar work, not measured values from this project, because the monitoring data belongs to the project owner. Alarm levels, instrument locations and reading frequencies must be set for each job by the design engineer based on its specific conditions.